BLD20-01025
| BLD-Footing | 4/6/2020 | 4/6/2020 | 4/6/2020 3:09:32 PM | P | PART |
|
|
clear call ahead and will pull plans out of trailer for you to look at // John Phone #: ###-####. Perimeter foorings, interior footings. Work is in progress. Will have special inspection. Noted RFI changes to footings have been submitted per the contractor and architect. Contractor to proceed at their own risk.
|
BLD18-00639
| BLD-Energy code compliance | 4/3/2020 | 4/6/2020 | 4/6/2020 2:24:11 PM | P | DEFR |
|
|
willing to facetime or photo // Dave Phone #: ###-####
|
BLD18-04071
| BLD-Framing/Rough-in | 4/3/2020 | 4/6/2020 | 4/6/2020 2:18:30 PM | P | PASS |
|
|
Framing and rock wool inspection for building 7 Phone #: ###-#### Inspection requested via web by chad stradley
|
BLD20-01026
| BLD-Final | 4/6/2020 | 4/6/2020 | 4/6/2020 1:16:39 PM | P | PASS |
|
|
screened // Tyson Phone #: ###-####
|
BLD20-01026
| DOC - Permit Finaled | 4/6/2020 | 4/6/2020 | 4/6/2020 1:15:56 PM | P | PASS |
|
|
|
BLD20-01026
| BLD-Framing/Rough-in | 4/6/2020 | 4/6/2020 | 4/6/2020 1:15:48 PM | P | PASS |
|
|
screened // Tyson Phone #: ###-####
|
BLD19-02949
| BLD-Final | 4/3/2020 | 4/6/2020 | 4/6/2020 10:25:22 AM | A | PASS |
|
|
Gene Phone #: ###-####
|
BLD19-04920
| BLD-Footing | 4/3/2020 | 4/6/2020 | 4/6/2020 9:33:33 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Interior column pad footings ok.
|
MIS20-00103
| BLD-Conference | 4/3/2020 | 4/6/2020 | 4/6/2020 9:12:12 AM | A | PASS |
|
|
|
MIS20-00103
| DOC - Permit Finaled | 4/6/2020 | 4/6/2020 | 4/6/2020 9:12:01 AM | P | PASS |
|
|
No work at this address other than a perimeter fence??
|
BLD20-00147
| BLD-Foundation | 4/3/2020 | 4/6/2020 | 4/6/2020 9:05:03 AM | A | PART |
|
|
cleared // Jerod Phone #: ###-####. Work is in progress.
|
BLD20-00153
| BLD-Framing/Rough-in | 4/1/2020 | 4/6/2020 | 4/6/2020 8:52:03 AM | A | NR |
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Needs electrical rough in inspection.
|