PLM05-01035
| Sprinkler (Final) | 4/6/2005 | 4/7/2005 | 4/7/2005 12:00:00 AM | A | PASS |
|
|
larry ###-#### sp final ok 4/7/2005 8:37:31 AM
|
PLM05-01036
| Sprinkler (Final) | 4/6/2005 | 4/7/2005 | 4/7/2005 12:00:00 AM | A | PASS |
|
|
###-#### - ryan sp final ok 4/7/2005 8:37:18 AM
|
PLM05-01037
| Sprinkler (Final) | 4/6/2005 | 4/7/2005 | 4/7/2005 12:00:00 AM | A | PASS |
|
|
###-#### - ryan sp final ok 4/7/2005 8:39:28 AM
|
PLM05-01042
| Water and/or Sewer | 4/6/2005 | 4/7/2005 | 4/7/2005 12:00:00 AM | A | PART |
|
|
sewer only chad ###-#### sewer ok 4/7/2005 9:03:14 AM
|
PLM05-01043
| Water and/or Sewer | 4/6/2005 | 4/7/2005 | 4/7/2005 12:00:00 AM | A | PART |
|
|
sewer only please chad ###-#### sewer ok 4/7/2005 9:03:05 AM
|
PLM05-01024
| Sprinkler (Final) | 4/6/2005 | 4/7/2005 | 4/7/2005 12:00:00 AM | A | PASS |
|
|
sp final ok 4/7/2005 9:30:24 AM
|
PLM05-01041
| Sprinkler (Final) | 4/6/2005 | 4/7/2005 | 4/7/2005 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 4/6/2005 at 8:08:28 PM. Contact: ###-####. sp final ok 4/7/2005 2:06:55 PM
|
PLM04-03699
| Final | 4/7/2005 | 4/7/2005 | 4/7/2005 12:00:00 AM | P | FAIL |
|
|
Scheduled by a contractor via Hello! on 4/7/2005 at 7:20:08 AM. Contact: ###-####. test dcva, thermol expantion protection required, avb is required to be above flood level of fixture. 4/7/2005 1:44:26 PM
|
PLM05-00984
| Water and/or Sewer | 4/7/2005 | 4/7/2005 | 4/7/2005 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 4/7/2005 at 7:22:46 AM. Contact: ###-####. sw final ok 4/7/2005 4:27:18 PM
|
PLM05-01049
| Plumbing Rough-in | 4/7/2005 | 4/7/2005 | 4/7/2005 12:00:00 AM | P | PASS |
|
|
###-#### - brett Note: early afternoon ri ok 4/7/2005 2:34:45 PM
|