BLD05-01409
| FIRE-Final Inspection | 4/6/2006 | 4/7/2006 | 4/7/2006 3:40:16 PM | P | PASS |
|
|
Life safety finaled
|
BLD06-00287
| FIRE-Final Inspection | 4/7/2006 | 4/7/2006 | 4/7/2006 3:21:35 PM | P | PASS |
|
|
life safety finaled
|
FIR06-00173
| INSP-Final Inspection | 4/7/2006 | 4/7/2006 | 4/7/2006 3:10:40 PM | P | FAIL |
|
|
Provide sprinkler head in the closet. Considered an occupiable space. No resubmittal required per troy.
|
FIR05-00644
| INSP-Sprinkler Rough-in | 4/6/2006 | 4/7/2006 | 4/7/2006 3:00:06 PM | A | PASS |
|
|
The stand pipes have been converted to wet. but the riser still needs to be installed in its final configuration.
|
FIR06-00183
| INSP-Alarm Testing | 4/7/2006 | 4/7/2006 | 4/7/2006 2:59:01 PM | P | FAIL |
|
|
four supervisory signal were sent but per the monitoring agency only three had been received. Need to test the elevator lobby smoke since it was relocated from the deck to the new ceiling.
|
FIR06-00038
| INSP-Final Inspection | 4/7/2006 | 4/7/2006 | 4/7/2006 2:58:04 PM | P | FAIL |
|
|
Need ceiling tile installed
|
FIR06-00065
| INSP-Sprinkler Rough-in | 4/6/2006 | 4/7/2006 | 4/7/2006 12:53:43 PM | A | CANC |
|
|
Inspection was supposed to be scheduled for monday.
|
FIR06-00045
| INSP-Final Inspection | 4/6/2006 | 4/7/2006 | 4/7/2006 12:52:57 PM | A | FAIL |
|
|
The inspection performed today was just for the changing of standard responce sprinkler heads to quick responce sprinkler heads in the light hazard areas of the plaza building basement. All heads appear to be changed. All heads that have been spot checked matched the data sheet provided. Heads inspected included the 200 degree pendants in the computer room. No other issues have been inspected except the sprinkler head change out.
|
BLD06-00015
| FIRE-Final Inspection | 4/6/2006 | 4/7/2006 | 4/7/2006 11:49:29 AM | A | FAIL |
|
|
Provide sprinkler head in the closet next to the secretary. Considered an occupiable space. Provide suite number.
|
FIR06-00140
| INSP-Sprinkler Rough-in/Hydro | 4/6/2006 | 4/7/2006 | 4/7/2006 10:51:08 AM | A | PART |
|
|
Piping above the hardlid areas as marked on plans is ok to cover.
|
FIR06-00061
| INSP-Final Inspection | 4/6/2006 | 4/7/2006 | 4/7/2006 10:24:26 AM | A | FAIL |
|
|
Could not contact dave brown since he takes fridays off and todd woods was not available. I showed up at job site and the found no secretary at the front desk and that the drawings are locked in FACP cabinet. No inspection performed.
|
BLD05-00978
| FIRE-Final Inspection | 4/6/2006 | 4/7/2006 | 4/7/2006 9:59:12 AM | A | PART |
|
|
Plant manager ken goicoechea and jim ross signed for and verified the piping pressure tests, verified piping type/compatibility, color code and marking of the piping, verification of the PNID, installation and calabration of critical equipment, high level lime/sump alarm, acetone tank (seismic bracing not required per IBC), generator relief valves, compressor pressure switch verified, pressure relief verified on the discharge piping, transmission belts are of the static conducting type, piping pressure test conducted per ANSI B31.3 per documentation, matrix provided. Per jim ross the sensors will be tested monthly until a history is set and then at the manufactures recommendations. I have either verified the paper documentation or have witness the above items visually. Per Dave Hanniman a temporary occupancy is ok pending the repair of the north east exit sign/emergency light. Fire extinguishers at the field dock are to be mounted as discussed.
|