Inspections for the day of: Monday, April 8, 1996.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAlan Hauser
TitleMEC-COM/RES INSPECTOR
Phone #794-9453
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC96-01004 INSP - Framing/ Rough-in4/5/19964/8/19964/8/1996 12:00:00 AMANR
04/05/96 350 -
MEC96-01005 INSP - Framing/ Rough-in4/5/19964/8/19964/8/1996 12:00:00 AMAPASS
04/05/96 350 - ROUGH-IN IS OK FOR THE OFFICES ON THE NORTHSIDE OF 4TH FLOOR. OFFICES O SOUTHSIDE NOT READY YET AND ANOTHER PERMIT NUMBER.
MEC96-01016 INSP - Framing/ Rough-in4/8/19964/8/19964/8/1996 12:00:00 AMPNR
04/08/96 350 - INSTALL NEW VAV BOXES (2) AND ACCESSORIES YMC JOB #M-4797 WORKMAN PAGER ###-####-BLD96-0034-$39,900.00 1ST FLOOR REMODEL
MEC96-01020 INSP - Gas pressure test4/8/19964/8/19964/8/1996 12:00:00 AMPCANC
04/08/96 350 - INSTALLING GAS PIPING TO 2 UNIT HEATERS IN TRUCK BAT UNIT INSTALLED BY BOISE CITY-$1,118.00-TRUCK BAY AND AT GAS METER THIS INSPECTION DONE BY DAVE LIGHTFOOT
MEC95-02057 INSP - Final4/8/19964/8/19964/8/1996 12:00:00 AMPPASS
04/08/96 350 - FINAL
MEC95-02057 INSP - Final4/8/19964/8/19964/8/1996 12:00:00 AMPPASS
04/08/96 350 - FINAL
MEC96-00146 INSP - Final4/8/19964/8/19964/8/1996 12:00:00 AMPPASS
04/08/96 350 - FINAL
MEC96-00146 INSP - Final4/8/19964/8/19964/8/1996 12:00:00 AMPPASS
04/08/96 350 - FINAL
MEC96-00383 INSP - Framing/ Rough-in4/8/19964/8/19964/8/1996 12:00:00 AMPPASS
04/08/96 350 - ROUGH-IN IS OK