Inspections for the day of: Wednesday, April 8, 2009.
Number of inspections: 9
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR09-00097 INSP-Alarm Testing4/8/20094/8/20094/9/2009 10:30:27 AMPCANC
The wrong inspection number was called in.
FIR08-00675 INSP-Sprinkler Rough-in4/8/20094/8/20094/8/2009 4:37:18 PMPPASS
The second and third floor sprinkler rough-in passed.
FIR09-00129 INSP-Final Inspection4/8/20094/8/20094/8/2009 4:22:02 PMPPASS
Permit finaled
FIR09-00125 INSP-Sprinkler Rough-in/Hydro4/8/20094/8/20094/8/2009 2:43:15 PMPFAIL
The above ground hydro test failed.
BLD09-00432 FIRE-Final Inspection4/7/20094/8/20094/8/2009 2:42:02 PMAPASS
life safety passed.
FIR07-00745 INSP-Conference4/8/20094/8/20094/8/2009 12:37:02 PMPDONE
I spoke to Jack about a timeline to get the inspection completed and the requirement for an updated map at the facp to reflect the changes. He stated the inspection would be completed next week.
FIR08-00675 INSP-Sprinkler Rough-in/Hydro4/7/20094/8/20094/8/2009 11:33:22 AMAPASS
The overhead hydro test passed.
FIR09-00058 INSP-Final Inspection4/7/20094/8/20094/8/2009 10:51:58 AMAPASS
permit finaled
FIR09-00129 INSP-Sprinkler Rough-in/Hydro4/7/20094/8/20094/8/2009 10:24:25 AMAPASS
sprinkler rough-in and hydro test passed.