BLD10-00036
| BLD-Aging Inspection | 4/8/2010 | 4/8/2010 | 4/8/2010 4:19:46 PM | | NR |
|
|
|
BLD09-02146
| BLD-Aging Inspection | 4/8/2010 | 4/8/2010 | 4/8/2010 4:18:54 PM | | PASS |
|
|
work is in progress, homeowner doing work.
|
BLD10-00278
| BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 4:17:24 PM | P | CANC |
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD10-00277
| BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 4:17:15 PM | P | CANC |
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD10-00276
| BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 4:17:04 PM | P | CANC |
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
|
ESC10-00123
| BMP Violation | 4/8/2010 | 4/8/2010 | 4/8/2010 4:16:11 PM | P | PART |
|
|
Work in progress on cleanup.
|
ESC10-00122
| BMP Violation | 4/8/2010 | 4/8/2010 | 4/8/2010 4:15:48 PM | P | PART |
|
|
Work in progress on cleanup.
|
ESC10-00121
| BMP Violation | 4/8/2010 | 4/8/2010 | 4/8/2010 4:15:32 PM | P | PART |
|
|
Work in progress on cleanup.
|
ESC10-00120
| BMP Violation | 4/8/2010 | 4/8/2010 | 4/8/2010 4:15:16 PM | P | PART |
|
|
Work in progress on cleanup.
|
ESC10-00071
| BMP Violation | 4/8/2010 | 4/8/2010 | 4/8/2010 4:14:59 PM | P | PART |
|
|
Work in progress on cleanup.
|
ESC10-00067
| BMP Violation | 4/8/2010 | 4/8/2010 | 4/8/2010 4:14:44 PM | P | PART |
|
|
Work in progress on cleanup.
|
BLD10-00179
| BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 4:13:10 PM | P | PASS |
|
|
FAce layer of 5/8 type x rock for 2hr. firewall, remaining side, second floor.
|
BLD10-00176
| BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 4:11:55 PM | P | NR |
|
|
|
BLD10-00279
| BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 2:47:23 PM | P | PASS |
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####. BAse and face layers of 5/8 type x rock for 2hr. firewall, remaining side, 1st. floor.
|
ESC10-00074
| BMP Violation | 4/8/2010 | 4/8/2010 | 4/8/2010 2:38:49 PM | P | PART |
|
|
Work in progress on cleanup.
|
ESC10-00073
| BMP Violation | 4/8/2010 | 4/8/2010 | 4/8/2010 2:37:09 PM | P | PART |
|
|
Work in progress on cleanup.
|
ESC10-00075
| BMP Violation | 4/8/2010 | 4/8/2010 | 4/8/2010 2:35:51 PM | P | PART |
|
|
Work in progress on cleanup.
|
BLD10-00183
| BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 12:09:55 PM | A | CANC |
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD10-00182
| BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 12:09:43 PM | A | CANC |
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD10-00181
| BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 12:09:25 PM | A | CANC |
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD10-00179
| BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 11:42:16 AM | A | PASS |
|
|
base layer of 5/8 type x rock for 2hr. firewall, 2nd. floor, remaining side.
|
BLD10-00176
| BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 11:40:52 AM | A | PASS |
|
|
base layer of 5/8 type x rock for 2hr. firewall, 2nd. floor, remaining side.
|
BLD10-00180
| BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 11:39:21 AM | A | CANC |
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD09-01275
| BLD-Other | 4/7/2010 | 4/8/2010 | 4/8/2010 9:49:04 AM | A | PASS |
|
|
rob - ceiling grid Phone #: ###-####. Reinspected grid ceiling. grid as installed per cisca 0-2 ok. Received letter from CASCO (architect of record) noting that CISCA 0-2 system is approved to be installed in leiu of the CICSCA3-4. Will have letter scanned into project.
|