ELE18-02665
| Electrical Rough-In | 4/8/2019 | 4/8/2019 | 4/8/2019 2:21:01 PM | P | PASS |
|
|
ON SITE CONTACT RICH BAIL CEILING ROUGH IN INSPECTION FOR THE SOUTH BATHROOM Phone #: ###-#### Inspection requested via web by Deb Gooden...grid ok
|
ELE19-01178
| Temporary Service | 4/6/2019 | 4/8/2019 | 4/8/2019 2:10:56 PM | P | PASS |
|
|
So sorry. The previous inspection was called in prematurely by the GC. Phone #: ###-#### Inspection requested via web by David McClellan t/s u/g new ok
|
ELE19-01157
| Temporary Service | 4/5/2019 | 4/8/2019 | 4/8/2019 1:58:30 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Emmet Bushman... t/s u/g new ok
|
ELE19-01156
| Temporary Service | 4/5/2019 | 4/8/2019 | 4/8/2019 1:58:01 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Emmet Bushman... t/s u/g new ok
|
ELE19-01155
| Temporary Service | 4/5/2019 | 4/8/2019 | 4/8/2019 1:57:21 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Emmet Bushman... t/s u/g new ok
|
ELE19-00917
| Rough-In Permanent Service | 4/8/2019 | 4/8/2019 | 4/8/2019 1:06:08 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by steve sellers... rough ok to cover p/s o/h new location ok
|
ELE19-01218
| Temporary Service | 4/5/2019 | 4/8/2019 | 4/8/2019 12:54:16 PM | A | NR |
|
|
Phone #: ###-#### Inspection requested via web by Therrin Robertson.... ground rod removed by excavator
|
ELE19-01217
| Temporary Service | 4/5/2019 | 4/8/2019 | 4/8/2019 12:54:15 PM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Therrin Robertson... t/s bu/g new ok
|
ELE14-00717
| Final | 4/4/2019 | 4/8/2019 | 4/8/2019 12:21:22 PM | A | PASS |
|
|
Final Inspection For Swimming Pool Any Questions Please Call Louis @ ###-#### Phone #: ###-#### Inspection requested via web by Louis Keller... ok to final
|
ELE19-01221
| Permanent Service | 4/5/2019 | 4/8/2019 | 4/8/2019 10:37:41 AM | A | CANC |
|
|
Phone #: ###-#### Inspection requested via web by Winters LLC.... wrong inspection scheduled
|
ELE19-01221
| Final | 4/5/2019 | 4/8/2019 | 4/8/2019 10:17:12 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Winters LLC... ok to final
|
ELE19-01221
| Electrical Rough-In | 4/8/2019 | 4/8/2019 | 4/8/2019 10:16:54 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Winters LLC... piping out of all in one to disconnect all work on surface
|
ELE19-00683
| Final | 4/4/2019 | 4/8/2019 | 4/8/2019 9:17:04 AM | A | FAIL |
|
|
re inspection Phone #: ###-#### Inspection requested via web by Icon Electric... corrections not made...next inspection will include reinspection fee if not corrected
|
MIS19-00089
| ELE-Conference | 4/5/2019 | 4/8/2019 | 4/8/2019 8:54:58 AM | A | PASS |
|
|
discussed with daycare owner and wife of building owner...did not know electrician working on job had not pulled a permit...will call and make sure permit is pulled...check back at end of week...scheduled inspection
|
ELE19-00676
| Electrical Rough-In | 4/5/2019 | 4/8/2019 | 4/8/2019 8:22:17 AM | A | PASS |
|
|
Mitch Phone #: ###-####... rough ok to cover...new addition dwn stairs and up stairs bedrooms
|