FIR02-00081
| INSP-Sprinkler Rough-in/Hydro | 4/8/2002 | 4/9/2002 | 4/9/2002 12:00:00 AM | A | CANC |
|
|
Scheduled by a contractor via Hello! on 04/08/2002 at 09:43:48. Contact: ###-####. per Bill - no inspections on overhead; underground approved for install and overhead requires resubmittal 4/9/2002 11:00:38 AM
|
BLD02-00202
| FIRE-Final Inspection | 4/8/2002 | 4/9/2002 | 4/9/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 04/08/2002 at 11:53:21. Contact: ###-####.
|
BLD02-00419
| FIRE-Final Inspection | 4/8/2002 | 4/9/2002 | 4/9/2002 12:00:00 AM | P | PASS |
|
|
fire fn doug ###-####
|
FIR02-00072
| INSP-Final Inspection | 4/8/2002 | 4/9/2002 | 4/9/2002 12:00:00 AM | P | NR |
|
|
Scheduled by a contractor via Hello! on 04/08/2002 at 16:28:35. Contact: ###-####. plans not on site will reschedule 4/9/2002 3:33:52 PM
|
BLD01-02204
| FIRE-Final Inspection | 4/9/2002 | 4/9/2002 | 4/9/2002 12:00:00 AM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 04/09/2002 at 07:36:22. Contact: ###-####. called the number and the contractor wanted a building final - fire not required for sign off 4/9/2002 8:09:14 AM
|
BLD01-00606
| FIRE-Final Inspection | 4/9/2002 | 4/9/2002 | 4/9/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 04/09/2002 at 08:02:13. Contact: ###-####.
|
BLD01-00597
| FIRE-Final Inspection | 4/9/2002 | 4/9/2002 | 4/9/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 04/09/2002 at 08:04:11. Contact: ###-####.
|
MIS02-00082
| FIR-Final | 4/9/2002 | 4/9/2002 | 4/9/2002 12:00:00 AM | P | PASS |
|
|
###-#### Jim
|
BLD02-00276
| FIRE-Conference | 4/9/2002 | 4/9/2002 | 4/9/2002 12:00:00 AM | P | PART |
|
|
Scheduled by Inspector: 409 On 4/9/2002 9:14:14 AM met with Cheryl of Erstad and went through the plans for exit signs; emergency lights; door hardware and kitchen requirements; basement sprinklers are overspaced and several areas unprotected; called Jsson about it and he said the exiting was based on full sprinklers from the basement; called Cheryl and told her the basement will have to be fully sprinklered 4/9/2002 3:33:28 PM
|
BLD97-01576
| FIRE-Final Inspection | 4/5/2002 | 4/9/2002 | 4/9/2002 12:00:00 AM | P | CANC |
|
|
Scheduled by a contractor via Hello! on 04/05/2002 at 12:20:51. Contact: ###-####.
|