BLD07-02387
| FIRE-Final Inspection | 4/8/2008 | 4/9/2008 | 4/9/2008 4:39:30 PM | A | PASS |
|
|
Life safety passed.
|
FIR08-00147
| INSP-Alarm Testing | 4/9/2008 | 4/9/2008 | 4/9/2008 4:38:44 PM | P | PASS |
|
|
permit finaled
|
FIR08-00237
| INSP-Conference | 4/8/2008 | 4/9/2008 | 4/9/2008 2:56:30 PM | A | DONE |
|
|
The first time I stopped at the project the facp was not dialing out to the monitoring station. I returned acouple of hours later and the problem, wiring related, had been fixed. I verified signals with the monitoring station. I also pointed out that the manual pull station was mounted too high and the technicians had lowered at by the time I arrived for my second inspection. I notified sam rogers and mark sentenno.
|
BLD07-02347
| FIRE-Final Inspection | 4/8/2008 | 4/9/2008 | 4/9/2008 12:22:41 PM | A | PASS |
|
|
Life safety passed.
|
BLD07-01230
| FIRE-Final Inspection | 4/8/2008 | 4/9/2008 | 4/9/2008 12:21:54 PM | A | PASS |
|
|
life safety passed
|
BLD07-01229
| FIRE-Final Inspection | 4/8/2008 | 4/9/2008 | 4/9/2008 12:19:38 PM | A | FAIL |
|
|
Provide emergency lighting throughout the central lobby area/waiting area as discussed. Provide resubmitted floor plans if required by the structural inspector. All other items are passed.
|
FIR08-00242
| INSP-Final Inspection | 4/8/2008 | 4/9/2008 | 4/9/2008 11:24:18 AM | A | PASS |
|
|
permit finaled.
|