Inspections for the day of: Thursday, April 9, 2015.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEvan Jenkins
TitleEROSION CONTROL MANAGER
Phone #794-3958
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC14-00438 General Inspection4/9/20154/9/20154/9/2015 2:13:18 PM PASS
WIP: BMP's still in place, permit still posted. No discharges leaving the stie
ESC15-00303 Site Preparation4/9/20154/9/20154/9/2015 12:39:11 PMPFAIL
John Phone #: ###-####
Grading took place earlier this morning prior to contractor picking up his permits from City Hall. Some minor trackout occuring that needs to be swept up, and new drop inlet protection needs to be installed along Canyon Creek St.
ESC12-00403 General Inspection4/9/20154/9/20154/9/2015 12:04:19 PM PASS
WIP: New office building is currently being constructed. No ESC issues observed at this time
ESC14-00882 DOC - Permit Finaled4/9/20154/9/20154/9/2015 9:13:58 AMPPASS
Project is complete
Some minor exterior painting to finished, but no earth disturbance. possibliity of offsite discharge is next to none.
complete
ESC14-01000 Aging Inspection4/9/20154/9/20154/9/2015 9:02:13 AM PASS
ESC14-01000 DOC - Permit Finaled4/9/20154/9/20154/9/2015 9:01:56 AMPPASS
Project Complete
Vegetation re-established via landscaping/sod
No ESC issues. Home is occupied
ESC14-00974 Aging Inspection4/9/20154/9/20154/9/2015 8:49:02 AM PASS
Project is approximately 90% complete. Only 1 home currently being finished up. Streets have been recently swept. No ESC issues at this time
ESC14-01021 Aging Inspection4/9/20154/9/20154/9/2015 8:23:04 AM PASS
ESC14-01021 DOC - Permit Finaled4/9/20154/9/20154/9/2015 8:22:50 AMPPASS
Demo Complete
No ESC issues
ESC14-00823 General Inspection4/8/20154/9/20154/9/2015 8:21:04 AMAPASS
WIP through out the whole WWTP. No ESC issues have been occuring.