Inspections for the day of: Monday, May 1, 2017.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Page
TitleFIRE INSPECTOR
Phone #208-914-5431
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR17-00153 INSP-Sprinkler Rough-in4/28/20175/1/20175/1/2017 3:07:26 PMPPART
Rough iinspection complete for overhead fire sprinkler piping, rough to cover will be scheduled when finish pendant/arm overs are installed.
FIR16-00299 INSP-Sprinkler Rough-in4/27/20175/1/20175/1/2017 3:04:50 PMPPART
Rough to cover inspection for overhead fire sprinkler piping/pendant heads located in level 1 lobby complete, approved for cover.
NAF17-00029 INSP-Sprinkler Rough-in/Hydro5/1/20175/1/20175/1/2017 12:17:07 PMPPASS
Underground hydro complete
NAF17-00029 INSP-Supply line flush5/1/20175/1/20175/1/2017 12:15:55 PMPDONE
Supply line flush complete
BLD16-00473 FIRE-Conference4/28/20175/1/20175/1/2017 11:14:21 AMAPART
Fire conference complete, awaiting answer from fire sprinkler plan reviewer for acceptance of proposed method to prevent pipe from freezing over top of breezeway.
NAF16-00084 INSP-Sprinkler Rough-in/Hydro4/28/20175/1/20175/1/2017 11:11:50 AMAPASS
Tenting inspection complete, overhead fire sprinkler piping approved for cover.
FIR17-00168 INSP-Final Inspection5/1/20175/1/20175/1/2017 9:17:51 AMAPASS
Final fire sprinkler inspection for area of work complete.
FIR17-00168 INSP-Sprinkler Rough-in4/27/20175/1/20175/1/2017 9:17:24 AMAPASS
Rough in inspection for overhead fire sprinkler piping in area of work complete.