FIR17-00153
| INSP-Sprinkler Rough-in | 4/28/2017 | 5/1/2017 | 5/1/2017 3:07:26 PM | P | PART |
|
|
Rough iinspection complete for overhead fire sprinkler piping, rough to cover will be scheduled when finish pendant/arm overs are installed.
|
FIR16-00299
| INSP-Sprinkler Rough-in | 4/27/2017 | 5/1/2017 | 5/1/2017 3:04:50 PM | P | PART |
|
|
Rough to cover inspection for overhead fire sprinkler piping/pendant heads located in level 1 lobby complete, approved for cover.
|
NAF17-00029
| INSP-Sprinkler Rough-in/Hydro | 5/1/2017 | 5/1/2017 | 5/1/2017 12:17:07 PM | P | PASS |
|
|
Underground hydro complete
|
NAF17-00029
| INSP-Supply line flush | 5/1/2017 | 5/1/2017 | 5/1/2017 12:15:55 PM | P | DONE |
|
|
Supply line flush complete
|
BLD16-00473
| FIRE-Conference | 4/28/2017 | 5/1/2017 | 5/1/2017 11:14:21 AM | A | PART |
|
|
Fire conference complete, awaiting answer from fire sprinkler plan reviewer for acceptance of proposed method to prevent pipe from freezing over top of breezeway.
|
NAF16-00084
| INSP-Sprinkler Rough-in/Hydro | 4/28/2017 | 5/1/2017 | 5/1/2017 11:11:50 AM | A | PASS |
|
|
Tenting inspection complete, overhead fire sprinkler piping approved for cover.
|
FIR17-00168
| INSP-Final Inspection | 5/1/2017 | 5/1/2017 | 5/1/2017 9:17:51 AM | A | PASS |
|
|
Final fire sprinkler inspection for area of work complete.
|
FIR17-00168
| INSP-Sprinkler Rough-in | 4/27/2017 | 5/1/2017 | 5/1/2017 9:17:24 AM | A | PASS |
|
|
Rough in inspection for overhead fire sprinkler piping in area of work complete.
|