Inspections for the day of: Tuesday, May 1, 2018.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorMark Moncarr
TitleELE-INSPECTOR
Phone #685-9023
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE18-01314 Final5/1/20185/1/20185/1/2018 1:55:51 PMPPASS
Replaced 2x4 grid fixtures and strip fluorescents. Please call Tyler Reed for specifics ###-####. Phone #: ###-#### Inspection requested via web by Scott Campbell Ok final LED lighting throughout.
ELE18-01547 Electrical Rough-In5/1/20185/1/20185/1/2018 1:41:57 PMPPASS
bathroom wall RI Phone #: ###-#### Inspection requested via web by kendall bender Ok cover 2 baths, 1 new wall and corner wall in SE corner of store.
ELE18-00771 Electrical Rough-In5/1/20185/1/20185/1/2018 12:49:16 PMPPASS
Please inspect floor heat in master bathroom. Thank you Shaun ###-#### Phone #: ###-#### Inspection requested via web by Shaun Kirkman Ok cover floor heat mstr.
ELE17-03019 Final4/30/20185/1/20185/1/2018 12:29:46 PMPPASS
Final Electrical inspection. All phases of Electrical have been trimmed. Customer has not installed floors or done touch up on home, however all Electrical has been completed and Trimmed. Phone #: ###-#### Inspection requested via web by Anastacio Fuentes Ok final.
ELE18-01418 Electrical Rough-In5/1/20185/1/20185/1/2018 12:15:35 PMPPASS
Inspection for master bath floor heat. For access please call Tom 1/2 hr prior to inspection. ###-#### Phone #: ###-#### Inspection requested via web by Terry Scott Ok cover floor heat mstr upstairs.
ELE18-01630 Final4/30/20185/1/20185/1/2018 11:46:14 AMAPASS
Phone #: ###-#### Inspection requested via web by Mike Okamura Ok final. Inside garage not sheetrocked. No wires running horizontal. 1 new 20a circuit ran to power recepts. Existing outside light blanked and used to re-feed garage ceiling lights.
ELE18-01629 Temporary Service4/30/20185/1/20185/1/2018 10:29:35 AMAPASS
Phone #: ###-#### Inspection requested via web by kevin blackmon t/s u/g n ok
ELE18-01625 Electrical Rough-In4/30/20185/1/20185/1/2018 10:03:04 AMAPASS
Underground inspection Phone #: ###-#### Inspection requested via web by steve ragan Ok cover trench.
ELE18-01144 Electrical Rough-In4/26/20185/1/20185/1/2018 9:21:53 AMAPASS
Austin will be at this rough ; final electrical inspection Phone #: ###-#### Inspection requested via web by BRS Permitting Ok cover. Installers were onsite and had a panel pulled from roof. All items UL listed.
ELE18-01144 Final5/1/20185/1/20185/1/2018 9:21:13 AMAPASS
Ok final.
ELE18-01614 Final4/30/20185/1/20185/1/2018 9:20:37 AMACANC
Please contact Eric Brown with any questions. Phone #: ###-#### Inspection requested via web by Bonnie Page Changed inspection to temp service. Idaho Power will get notified otherwise. Temp poles automatically final out once energized.
ELE18-01614 Temporary Service5/1/20185/1/20185/1/2018 9:19:36 AMAPASS
t/s u/g n ok.
ELE17-04256 Electrical Rough-In5/1/20185/1/20185/1/2018 8:42:25 AMAPASS
floor heat Phone #: ###-#### Inspection requested via web by Dan Rohl Ok cover floor heat mstr.
ELE18-00988 Final5/1/20185/1/20185/1/2018 7:43:51 AMACANC
Pls contact Bryce (Foreman) @ ###-#### or George (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. >> Inspection requested via web by Rob Maes Inspection cancelled from web by: Rob Maes
ELE13-03208 ELE-Aging Inspection5/1/20185/1/20185/1/2018 7:09:47 AM PASS
Please schedule a final inspection.
ELE13-03342 ELE-Aging Inspection5/1/20185/1/20185/1/2018 7:08:44 AM DONE
Please schedule a final inspection.
ELE18-01518 Final4/25/20185/1/20185/1/2018 12:00:00 AMACANC
Homeowner will be home. MSP in garage. Phone #: ###-#### >> Inspection requested via web by BRS Permitting
ELE18-01606 Electrical Rough-In4/30/20185/1/20184/30/2018 2:37:56 PMAPASS
Ufer Phone #: ###-#### Inspection requested via web by Stephanie Huston Ok cover. Looked at on 4/30/18. 3/0 ufer attached rebar. Concrete was to be poured early morning of 5/1/18.