Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
PLM07-00733 Plumbing Rough-in5/10/20075/10/20075/10/2007 5:11:37 PMPPASS
ken; Phone #: ###-#### Internet Inspection Request from: Victoria Beall NOTE above floor rough-in test ok going to pass so home owner can proceed with work above floor still need to make correction on DWV drainage under floor inspector 380 will check on final as per conversation with Eric
PLM05-04309 Plumbing Rough-in5/10/20075/10/20075/10/2007 4:15:11 PMPPART
Scheduled by a contractor via Hello! on 5/10/2007 at 8:15:07 AM. Contact: ###-####. 9th floor bunder floor DWV for room,s 97306,08,09,10,and 11 test ok all 9th floor under floor DVW is done
PLM07-00167 Final5/10/20075/10/20075/10/2007 3:05:53 PMPPASS
Scheduled by a contractor via Hello! on 5/10/2007 at 10:53:59 AM. Contact: ###-####.
PLM07-00254 Final5/10/20075/10/20075/10/2007 3:05:38 PMPPASS
Scheduled by a contractor via Hello! on 5/10/2007 at 10:53:00 AM. Contact: ###-####.
PLM07-00917 Plumbing Rough-in5/10/20075/10/20075/10/2007 1:59:56 PMPPASS
PLM07-00803 Final5/10/20075/10/20075/10/2007 12:14:16 PMPPART
jeremy; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt need ice machine and all other water supplied equipment installed - additional back flow for equipment may be required need to caulk all fixture,s to wall oked temp.
PLM07-01238 Water and/or Sewer5/10/20075/10/20075/10/2007 11:16:44 AMAPART
Scheduled by a contractor via Hello! on 5/10/2007 at 6:36:12 AM. Contact: ###-####. new water line test ok ok to cover
PLM06-02796 Final5/9/20075/10/20075/10/2007 10:17:32 AMAPASS
fred; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
PLM07-01312 Final5/9/20075/10/20075/10/2007 9:50:34 AMAPASS
Sean Hart is the field contact. Need final Inspection for temp water line to job trailer. Phone #: ###-#### Internet Inspection Request from: Heidi Mallet
PLM07-00917 Plumbing Rough-in5/9/20075/10/20075/10/2007 9:21:08 AMAFAIL
ron ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith test failed on dwv need to repipe ejector discharge to an approved location