Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR13-00100 INSP-Final Inspection5/8/20135/10/20135/10/2013 3:51:51 PMPPASS
Permit finaled
BLD12-00382 FIRE-Final Inspection5/9/20135/10/20135/10/2013 3:36:55 PMPPART
The "accounting" area and the temporary exit corridor has passed life safety.
FIR13-00070 INSP-Sprinkler Rough-in/Hydro5/9/20135/10/20135/10/2013 3:30:30 PMPPASS
Wet system hydro test passed
FIR13-00074 INSP-Sprinkler Rough-in5/9/20135/10/20135/10/2013 3:06:54 PMPPASS
This is a rough to cover for the 1st floor. See the city approved plans for locations where piping can be covered.
FIR13-00164 INSP-Sprinkler Rough-in5/10/20135/10/20135/10/2013 2:27:43 PMPPASS
See the city approved plans for locations where piping can be covered.
FIR13-00163 INSP-Sprinkler Rough-in5/10/20135/10/20135/10/2013 12:35:45 PMPPASS
See the city approved plans for locations where piping can be covered.
FIR13-00177 INSP-Sprinkler Rough-in5/10/20135/10/20135/10/2013 11:19:18 AMPPASS
Sprinkler piping is ok to cover.
BLD13-01108 FIRE-Final Inspection5/10/20135/10/20135/10/2013 11:15:19 AMPPASS
Life safety passed. The fire extinguisher is on the way and being provided by Don at Fire extreme.
FIR12-00583 INSP-Supply line flush5/9/20135/10/20135/10/2013 9:52:52 AMAPASS
The underground flush for the four north most units passed.