Inspections for the day of: Friday, May 10, 2019.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorEric Story
TitleELE-INSPECTOR
Phone #985-3493
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE19-00595 Final5/10/20195/10/20195/10/2019 2:42:00 PMPPASS
garage code 2018 Phone #: ###-#### Inspection requested via web by Darryn Coburn
Final ok
ELE19-01484 Permanent Service5/8/20195/10/20195/10/2019 1:56:41 PMPPASS
** RE-ENERGIZE INSP** Pls contact Barry (Electrician) @ ###-#### one hr prior to arrival. Power restored around 2-3pm. Thank you. Inspection requested via web by Rob Maes
p/s o/h rec ok
ELE19-01705 Final5/10/20195/10/20195/10/2019 1:45:15 PMPPASS
Call for access // Joe Phone #: ###-####
Final ok
ELE19-00801 Final5/10/20195/10/20195/10/2019 1:30:46 PMPPASS
Phone #: ###-#### Inspection requested via web by Sherry Allen
Final ok, card signed
ELE19-01716 Electrical Rough-In5/9/20195/10/20195/10/2019 12:58:43 PMPPASS
adding a new washer circuit and dryer circuit. I will be onsite. Phone #: ###-#### Inspection requested via web by Justin Yount
Rough-in ok for addtition of washer and dryer
ELE19-01703 Permanent Service5/10/20195/10/20195/10/2019 12:58:11 PMPPASS
please call 30 min prior Phone #: ###-#### Inspection requested via web by John Edwards
p/s o/h n ok
ELE19-00206 Final5/10/20195/10/20195/10/2019 12:02:28 PMPPASS
just need to close this one no work has been done other than pulling the meter for siding you look at if want but it will be the same as last inspection Phone #: ###-#### Inspection requested via web by dennis mcneely
Closing permit as nothing to look at
ELE19-01363 Final5/9/20195/10/20195/10/2019 12:01:55 PMAPASS
Please call two hours ahead to Sandra ###-#### if you can. Phone #: ###-#### Inspection requested via web by BRS Permitting
Solar Array final ok
ELE15-01664 Final5/9/20195/10/20195/10/2019 11:27:10 AMAPASS
Any Questions please call Louis at ###-#### Phone #: ###-#### Inspection requested via web by Louis Keller
Pool final ok
ELE19-01556 Final5/9/20195/10/20195/10/2019 11:07:43 AMAPASS
Phone #: ###-#### Inspection requested via web by BRS Permitting
Final ok
ELE19-01323 Final5/9/20195/10/20195/10/2019 10:49:26 AMAPASS
Phone #: ###-#### Inspection requested via web by Jason Wicks
Final ok
ELE19-01713 Conference5/9/20195/10/20195/10/2019 10:13:01 AMADONE
I need to meet inspector at this job site to go over a plan before we start work. Phone #: ###-#### Inspection requested via web by Barbara Szurgot
Discussed service change on 480/277V 800 amp service to be change out on memorial day weekend.... Building steel will be grounded and need to verify main grounding source in new service..... Gear will be less depth then what is currently install to maintain work space clearences.... All panels in shop to be switched out and was told no area of classification at this time as no storage of fuel is apparent....
ELE19-01327 Electrical Rough-In5/10/20195/10/20195/10/2019 9:46:03 AMAPASS
storefront Phone #: ###-#### Inspection requested via web by Bryan McLaughlin
Store front wall and cash wrap wall ok to cover