Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00062 INSP-Final Inspection5/10/20055/11/20055/11/2005 1:50:06 PMAPART
Rough-in above hard lid areas first floor cafe OK to cover. Grid ceiling and heads in grid ceiling areas not installed yet. Verify wood 2x4's above hard lid at south soffit are fire treated.
BLD05-00166 FIRE-Final Inspection5/11/20055/11/20055/11/2005 11:49:56 AMAPASS
Fire life safety finaled.
FIR05-00045 INSP-Sprinkler Rough-in5/10/20055/11/20055/11/2005 10:06:56 AMAFAIL
Overhead pipe installed does not match piping plan on approved drawings in front entry or 2nd floor main/branch line connections. Re-submit plans reflecting all field changes.
FIR05-00038 INSP-Supply line flush5/10/20055/11/20055/11/2005 9:58:02 AMACANC
Cancel inspection, wrong job permit called in.
FIR04-00593 INSP-Sprinkler Rough-in/Hydro5/11/20055/11/20055/11/2005 12:00:00 AMAPART
24 hour air test of preaction system passed within allowable 1 1/2 psi. loss. Preaction system valve appears to be installed as a single interlock, not double interlock as indicated on plan submittals.
FIR05-00045 INSP-Sprinkler Rough-in/Hydro5/11/20055/11/20055/11/2005 12:00:00 AMAFAIL
Underground fire supply main does not meet min. 4'-6" depth of bury requirements. Provide sleeve for EQ clearance through floor slab at riser. Cover bolts at MJ 90.