ESC08-01044
| BMP Violation | 5/11/2009 | 5/11/2009 | 5/11/2009 2:28:37 PM | P | FAIL |
|
|
Verbal to concrete contractor and to RP of project. No concrete washout and wet liquid residual on flat bare ground also someone had tracked out residual off the job site. Informed RP that in the future even with finishing of project that an acceptable containment facility will be required, example kiddie pool, poly lined berm, pit, etc. Concrete to removed and cleaned up within 24 hours.
|
ESC07-00904
| Random Inspection | 5/11/2009 | 5/11/2009 | 5/11/2009 2:15:36 PM | P | PART |
|
|
WIP-site not fully stabized.
|
ESC08-01050
| Random Inspection | 5/11/2009 | 5/11/2009 | 5/11/2009 1:43:46 PM | P | PART |
|
|
Informed RP-J.C. that concrete washout is in need of maintance. Overall site looks good.
|
ESC08-00486
| Site Preparation | 5/11/2009 | 5/11/2009 | 5/11/2009 1:18:15 PM | P | PART |
|
|
Should be final not site preparation; Landscaping in progress. could use a sediment barrier on west and north side of property.
|