Inspections for the day of: Monday, May 11, 2015.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorBob Reichert
TitleELE-INSPECTOR
Phone #794-1923
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ELE13-00942 ELE-Aging Inspection5/11/20155/11/20155/12/2015 10:19:27 AM DONE
still under construction
ELE14-01066 Electrical Rough-In5/8/20155/11/20155/11/2015 3:51:05 PMPPASS
Rough in inspection H 1st floor rooms H103, H104, H159, H160. Building permit number BLD13-00184. Call Lonny when on site. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum ok cover as requested
ELE14-01814 Final5/9/20155/11/20155/11/2015 3:33:01 PMPPART
Final electrical inspection IL 1st floor area C rooms C105, C106, C107, C108, C109, and C110. Building permit number BLD13-00182. Call Lonny when on site. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum rooms listed ok final
ELE15-01359 Final5/8/20155/11/20155/11/2015 2:23:57 PMPCANC
Contact: Dawn Wirz (owner) Please call before going. Phone #: ###-#### Inspection requested via web by Deb Gooden see ri
ELE15-01359 Electrical Rough-In5/11/20155/11/20155/11/2015 2:23:25 PMPPASS
Contact: Dawn Wirz (owner) Please call before going. Phone #: ###-#### Inspection requested via web by Deb Gooden circuit additions only ok, will final after remote shed done
ELE15-01168 Final5/11/20155/11/20155/11/2015 2:09:21 PMPCANC
Rae Phone #: ###-#### see final later, see rip
ELE15-01168 Rough-In Permanent Service5/11/20155/11/20155/11/2015 2:07:56 PMPPASS
Rae Phone #: ###-#### ri ok, ok cover u/g, p/s o/h rec ok
ELE15-01365 Electrical Rough-In5/11/20155/11/20155/11/2015 1:32:59 PMPPASS
Call Steve when in route. Check in with security at front desk. Phone #: ###-#### Inspection requested via web by Steve McCloy ok cover perimeter borders and walls only
ELE15-01363 Rough-In Permanent Service5/11/20155/11/20155/11/2015 1:06:41 PMPPASS
Phone #: ###-#### Inspection requested via web by kevin blackmon ri ok, p/s u/g n ok
ELE15-00724 Electrical Rough-In5/11/20155/11/20155/11/2015 11:51:01 AMPPASS
Floor heat Master bedroom; Jason Phone #: ###-#### ok cover floor heat only
ELE15-01328 Conference5/8/20155/11/20155/11/2015 10:47:58 AMADONE
would like call 30min ahead; Evon Phone #: ###-#### talked about wiring bath upstairs, code items like free length, 1 1/4", circuits, spacing outlets, when to call for inspections
ELE15-01349 Temporary Service5/11/20155/11/20155/11/2015 9:38:40 AMAPASS
Phone #: ###-#### Inspection requested via web by Greg Traudt t/s u/g n ok
ELE15-00784 Final5/8/20155/11/20155/11/2015 9:00:39 AMAPASS
This is just the circuit for a potential solar installation in the future.
There is a jbox in the attic, below the south facing roof of the garage where the solar would go. From there a single home run in conduit runs back to the knife switch located next to the meter base. And from the knife switch the breaker in panel A, at the bottom of the bussing, opposite the feeder lugs.
There is a lightning ground, that runs along side the solar conduit that is connected to the service electrode under the main panels in the garage.
Thanks again Phone #: ###-#### Inspection requested via web by Ryan King ok final
ELE15-01189 Rough-In Permanent Service5/8/20155/11/20155/11/2015 8:16:34 AMAPASS
Phone #: ###-#### Inspection requested via web by Bob Glenn ri ok, p/s u/g n ok