Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC09-00352 General Inspection5/12/20105/12/20105/12/2010 2:49:56 PMPPART
Main park area: Overall site looks ok, lots of area exposed and it's up to the contractor to determine if the existing conditions meet CGP regarding final stabilization. Work continuing to be worked on the north side of Wellings Creek. Willows along the river continue to have new growth. Minimal grass observed between the willows. No signs of areas where in normal rain event conditions that turbid discharge could occur.
ESC09-00352 General Inspection5/12/20105/12/20105/12/2010 1:46:53 PMPPART
Ped. bridge area: Verbal to RP, Sediment barriers needed in misc. locations both north and south of new bridge box culvert. Turbidity curtain remains downstream across Wellings Creek. Work to connect new spur of the Greeen Belt with the existing Green Belt is scheduled for the week of May 24th. Access road south of the Ped. Bridge is being constructed currently.
ESC10-00307 General Inspection5/12/20105/12/20105/12/2010 1:43:00 PMPPASS
Building debris has been removed from the site except concrete foundation, contractor working removal of the foundation during inspection. Sign posted.
ESC10-00312 Site Preparation5/12/20105/12/20105/12/2010 7:55:10 AM CANC
Inspection passed by inspector 330 on 5/10/10
ESC10-00377 Site Preparation5/12/20105/12/20105/12/2010 7:54:40 AM CANC
Inspection passed by inspector 415 on 5/10/10
ESC10-00323 Site Preparation5/12/20105/12/20105/12/2010 7:54:06 AM CANC