FIR15-00096
| INSP-Sprinkler Rough-in | 5/12/2015 | 5/13/2015 | 5/16/2015 9:39:30 AM | A | PASS |
|
|
Rough to cover for 3rd Floor West and visual insulation inspection on 2nd floor SW, including units 221-241, and units 319-339.
|
FIR14-00252
| INSP-Sprinkler Rough-in/Hydro | 5/12/2015 | 5/13/2015 | 5/16/2015 9:34:07 AM | P | PASS |
|
|
Kitchen rough-in inspection for levels 1 and 2
|
FIR14-00866
| INSP-Sprinkler Rough-in | 5/13/2015 | 5/13/2015 | 5/16/2015 9:30:54 AM | P | PASS |
|
|
Clubhouse rough-in inspection. No discrepancies noted.
|
FIR14-00815
| INSP-Sprinkler Rough-in/Hydro | 5/12/2015 | 5/13/2015 | 5/15/2015 2:54:19 PM | A | PASS |
|
|
Dry system hydrotest
|