MEC01-01034
| Final | 5/10/2001 | 5/14/2001 | 5/14/2001 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 05/10/2001 at 10:35:34. Contact: ###-####.--early am if possible ???? need comb air per manuf 5/14/2001 10:25:54 AM
|
MEC01-01148
| Rough-in | 5/11/2001 | 5/14/2001 | 5/14/2001 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 05/11/2001 at 12:18:30. Contact: ###-####.
|
MEC01-01148
| Pressure Test | 5/11/2001 | 5/14/2001 | 5/14/2001 12:00:00 AM | A | NR |
|
|
Scheduled by a contractor via Hello! on 05/11/2001 at 12:18:43. Contact: ###-####.
|
MEC01-01353
| Final | 5/11/2001 | 5/14/2001 | 5/14/2001 12:00:00 AM | A | NH |
|
|
Scheduled by a contractor via Hello! on 05/11/2001 at 14:14:54. Contact: ###-####.
|
MEC01-01401
| Rough-in | 5/11/2001 | 5/14/2001 | 5/14/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 05/11/2001 at 14:36:00. Contact: ###-####.
|
MEC01-01401
| Pressure Test | 5/11/2001 | 5/14/2001 | 5/14/2001 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 05/11/2001 at 14:36:32. Contact: ###-####.
|
MEC01-00390
| Final | 5/14/2001 | 5/14/2001 | 5/14/2001 12:00:00 AM | P | FAIL |
|
|
###-#### no r/i ever done on pellet stove..no specs on sight 5/14/2001 3:39:31 PM
|
MEC01-00358
| Final | 5/14/2001 | 5/14/2001 | 5/14/2001 12:00:00 AM | P | PASS |
|
|
###-####
|
MEC00-04368
| Final | 5/14/2001 | 5/14/2001 | 5/14/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 05/14/2001 at 09:38:27. Contact: ###-####.
|
MEC01-00911
| Final | 5/14/2001 | 5/14/2001 | 5/14/2001 12:00:00 AM | P | FAIL |
|
|
5/14/2001 11:33:44 AM prv to term outside..pull sod away from dryer vent term 5/14/2001 2:04:18 PM
|
MEC01-01326
| Conference | 5/14/2001 | 5/14/2001 | 5/14/2001 12:00:00 AM | P | PASS |
|
|
Added by Inspector: 411 On 5/14/2001 1:26:26 PM
|