Inspections for the day of: Friday, May 14, 2010.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD10-00661 FIRE-Conference5/13/20105/14/20105/14/2010 3:56:10 PMPCANC
To be rescheduled for monday per Marvin.
FIR03-00082 INSP-Conference5/11/20105/14/20105/14/2010 3:32:48 PMADONE
I left messages on Ron's and Jeff's voice mails requesting status of project. Follow up inspection at walmart scheduled for monday.
BLD10-01038 FIRE-Final Inspection5/14/20105/14/20105/14/2010 3:26:06 PMPPASS
Life safety passed. Fire extinguishers to be installed Monday per Rod Walters ###-####.
BLD10-00875 FIRE-Final Inspection5/13/20105/14/20105/14/2010 3:24:11 PMPFAIL
At my last visit to the job site I was told that the ADT technician had not programed the dialer for the facp yet. I told them to call me when completed so that we could verify signals.
BLD10-00260 FIRE-Final Inspection5/13/20105/14/20105/14/2010 3:21:16 PMAFAIL
One exit sign had not been installed out of the north exit and there was no access to the mechanical room to verify the exit sign shown to be installed. Could not verify battery backup function of the emergency lights or exit signs. All other items appear ok.
FIR10-00059 INSP-Final Inspection5/13/20105/14/20105/14/2010 3:19:00 PMAPASS
Permit finaled
FIR10-00214 INSP-Final Inspection5/14/20105/14/20105/14/2010 3:14:51 PMPCANC
Project is not ready for a final inspection. See the rough-in inspection entry.
FIR10-00214 INSP-Sprinkler Rough-in5/14/20105/14/20105/14/2010 3:11:39 PMPPASS
Sprinkler piping has been installed per plans. The new walls have not been installed yet can not final until wall/sprinkler coverage can be verified.
BLD10-00539 FIRE-Final Inspection5/13/20105/14/20105/14/2010 1:26:59 PMPFAIL
Provide single action lever hardware on both exit doors and provide a 2a,10bc fire extinguisher with current inspection tag as discussed.
FIR10-00185 INSP-Final Inspection5/14/20105/14/20105/14/2010 12:11:01 PMPFAIL
Three existing audio/visual devices have been installed with the lense below the minimum 80". When installed this was a code requirement. No testing was performed due to the modifications required.
BLD10-00031 FIRE-Final Inspection5/13/20105/14/20105/14/2010 11:43:20 AMAPART
Pool Restrooms Phase 2 life safety inspection passed.
FIR09-00707 INSP-Sprinkler Rough-in5/14/20105/14/20105/14/2010 11:42:13 AMPPASS
The fire sprinklers are complete in the pool/shower area.
FIR10-00060 INSP-Alarm Testing5/13/20105/14/20105/14/2010 11:41:16 AMAPASS
The fire alarm system in Phase 2 pool/restrooms is complete and tested ok. Additional strobe were required/added in the showers and restoom stalls. They will need to be shown on the resubmitted plans or as-builts which ever case it may be.
FIR09-00678 INSP-Final Inspection5/13/20105/14/20105/14/2010 8:45:13 AMAPASS
Permit finaled.
FIR09-00635 INSP-Alarm Testing5/14/20105/14/20105/14/2010 8:09:02 AMPDONE
Fire sprinkler risers #2 and #3 inspected today. Flow switches and tamper switches functioned correctly. These items are not shown on the fire alarm plans and will need to be included when the plan modifications are submitted prior to a final sign off.
FIR09-00611 INSP-Sprinkler Rough-in5/13/20105/14/20105/14/2010 8:08:00 AMAPASS
Fire sprinkler risers #2 and #3 inspected today. Flow switches and tamper switches functioned correctly. Noted that the backflow preventors need their certifications.
FIR10-00196 INSP-Sprinkler Rough-in5/13/20105/14/20105/14/2010 12:00:00 AMPDONE
Rough In Passed. The GC said he would put batt insulation over the piping first,over the visqueen and then the blow insulation.

Raul is the contact. Thanks Inspection requested from web by: Stan Beus Phone #: ###-####
FIR10-00099 INSP-Final Inspection5/13/20105/14/20105/13/2010 11:04:50 AMACANC
Tim Christopherson Inspection requested from web by: Diane Turner Phone #: ###-#### Inspection cancelled from web by: Diane Turner