ESC12-00460
| Site Preparation | 5/14/2012 | 5/14/2012 | 5/16/2012 2:38:23 PM | | NH |
|
|
|
ESC12-00364
| Site Preparation | 5/11/2012 | 5/14/2012 | 5/15/2012 1:27:15 PM | A | PART |
|
|
Verbal to RP: Install sediment barriers per industry standards prior to any storm events.
|
ESC11-00681
| BMP Violation | 5/11/2012 | 5/14/2012 | 5/15/2012 5:57:01 AM | A | PART |
|
|
Explained to RP that he is responsible for maintaining all BMP's and making sure any sediment leaving he project area and deposits on hard surfaces must be cleaned up by the end of the work day .
|
ESC11-00593
| Aging Inspection | 5/14/2012 | 5/14/2012 | 5/15/2012 5:54:52 AM | | PART |
|
|
NO activity.
|
ESC11-00361
| Aging Inspection | 5/14/2012 | 5/14/2012 | 5/15/2012 5:53:36 AM | | FAIL |
|
|
Verbal to RP: CLean up all hard surfaces of al sediment and debris through out the active construction area. Also where contractor have been placing of materials and spolis in the undeveloped portion of the project area to maintain and remove all trash debris from the lots. Will folllow up on 5/18/2012am.
|
ESC11-00176
| General Inspection | 5/14/2012 | 5/14/2012 | 5/14/2012 2:07:33 PM | | FAIL |
|
|
Verbal to RP/ GC (Mike Smith) CLean up all hard surfaces of all sediment and debris. Will re-inspect on 5/16/2012AM.
|
ESC11-00055
| General Inspection | 5/14/2012 | 5/14/2012 | 5/14/2012 11:05:34 AM | | PASS |
|
|
Spoke with RP ovr th stabilization methods applid and the re-application after flood waters receed. No violation found or concerns.
|