Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD14-02502 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:46:05 PMPPASS
permit finaled
BLD14-02519 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:44:08 PMPPASS
permit finaled
BLD14-02515 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:42:22 PMPPASS
permit finaled
BLD14-02514 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:41:23 PMPPASS
Permit finaled
BLD14-02508 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:39:13 PMPPASS
permit finaled
BLD14-02503 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:38:17 PMPPASS
Permit finaled
BLD14-02520 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:37:40 PMPPASS
Permit finaled
BLD14-02518 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:36:17 PMPPASS
Permit finaled
BLD14-02501 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:29:54 PMPPASS
Permit finaled
BLD14-02507 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:27:05 PMPPASS
Permit finaled
BLD14-02521 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:26:19 PMPPASS
permit finaled
BLD14-02432 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:25:31 PMPPASS
Permit finaled
BLD14-02510 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:24:29 PMPPASS
permit finaled
BLD14-02500 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:23:09 PMPPASS
permit finaled
BLD14-02517 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:19:48 PMPPASS
permit finaled
BLD14-02433 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:12:37 PMPPASS
Permit finaled
BLD14-02523 FIRE-Final Inspection5/14/20155/14/20155/15/2015 3:07:36 PMPPASS
permit finaled
BLD15-00521 FIRE-Final Inspection5/14/20155/14/20155/15/2015 2:56:20 PMPPASS
permit finaled
FIR15-00171 INSP-Sprinkler Rough-in5/13/20155/14/20155/14/2015 2:56:01 PMPPASS
Rough-in passed for the new Conference Room. Piping can be covered.
BLD15-01464 FIRE-Final Inspection5/14/20155/14/20155/14/2015 1:26:18 PMPPASS
life safety passed
FIR15-00328 INSP-Final Inspection5/13/20155/14/20155/14/2015 10:45:38 AMAPASS
permit finaled
FIR15-00328 INSP-Sprinkler Rough-in5/13/20155/14/20155/14/2015 10:34:34 AMAPASS
Rough-in passed
BLD15-01140 FIRE-Final Inspection5/13/20155/14/20155/14/2015 10:01:32 AMAFAIL
Provide tagged fire extinguisher, provide testing of the smoke evac system and the exit signs/emergency lights
BLD14-01408 FIRE-Final Inspection5/13/20155/14/20155/14/2015 9:59:30 AMAPASS
life safety passed
FIR15-00192 INSP-Final Inspection5/13/20155/14/20155/14/2015 9:52:06 AMAPASS
permit finaled
FIR14-00619 INSP-Final Inspection5/13/20155/14/20155/14/2015 9:51:53 AMAPASS
Permit finaled
FIR15-00314 INSP-Sprinkler Rough-in5/13/20155/14/20155/14/2015 9:16:38 AMAPART
The rough-in for the tenant space passed for the most part . Piping can be covered but additional upright protection is required around the room with no ceiling.
FIR14-00910 INSP-Final Inspection5/13/20155/14/20155/14/2015 9:13:00 AMAFAIL
No inspection was performed due to the fire alarm monitoring system not being complete. Also the tamper switch for the PIV has not been installed.
FIR15-00264 INSP-Sprinkler Rough-in/Hydro5/13/20155/14/20155/14/2015 8:54:09 AMAFAIL
Not ready for inspection due to the other fire alarm permit corrections.
FIR15-00254 INSP-Final Inspection5/13/20155/14/20155/14/2015 8:50:46 AMAFAIL
No testing performed. Duct smoke detectors are not wired up or tested, smoke detector at the FACP is mounted too far from the deck, the tamper switch fot the PIV is not installed. I have not looked at the approved drawings yet.
FIR14-00760 INSP-Sprinkler Rough-in5/13/20155/14/20155/14/2015 7:52:56 AMAPASS
Tenting passed. Piping can be covered.