Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MIS19-00106 MIS-Aging Inspection5/14/20205/14/20205/20/2020 12:07:05 PM CANC
BLD19-03180 BLD-Wall Bracing5/14/20205/14/20205/14/2020 3:48:57 PMPPASS
fire wall Inspection requested via web by Carl //interior shear on fire wall//screws/ nails ok per plans, compliant with engineers email stating blocking is not needed at edges//still need rating for ele heater box in rated wall//
BLD19-03181 BLD-Wall Bracing5/14/20205/14/20205/14/2020 3:48:37 PMPPASS
Inspection requested via web by Carl Funk//interior shear on fire wall//screws/ nails ok per plans, compliant with engineers email stating blocking is not needed at edges//still need rating for ele heater box in rated wall//
BLD19-03187 BLD-Wall Bracing5/14/20205/14/20205/14/2020 3:48:19 PMPPASS
Inspection requested via web by Carl Funk//interior shear on fire wall//screws/ nails ok per plans, compliant with engineers email stating blocking is not needed at edges//still need rating for ele heater box in rated wall//
BLD19-03188 BLD-Wall Bracing5/14/20205/14/20205/14/2020 3:48:00 PMPPASS
Inspection requested via web by Carl Funk//interior shear on fire wall//screws/ nails ok per plans, compliant with engineers email stating blocking is not needed at edges//still need rating for ele heater box in rated wall//
BLD20-00698 BLD-Framing/Rough-in5/14/20205/14/20205/14/2020 1:36:43 PMPPASS
Please call Sid ###-#### Phone #: ###-#### Inspection requested via web by Carissa Mattison//steel stud wall used, ele ok, add brace near doorway in new wall//wall framing only//will need Mechanical permit to add ducts for office area prior to grid inspection///
BLD19-04385 BLD-Final5/13/20205/14/20205/14/2020 11:14:49 AMANR
Phone #: ###-#### Inspection requested via web by John Treat//still needs blower door test//need to verify u values on windows are .31 for the R38, or R49 will be required for the .32 u value//
BLD20-00345 BLD-Conference5/13/20205/14/20205/14/2020 10:28:08 AMADONE
Rusty *screened* Phone #: ###-####//questions on the separation wall construction, was determined we need clarification from Architect on separation wall and extent of rating//also need detail for attachment on ledger and beams for loft//
MIS20-00142 BLD-Conference5/7/20205/14/20205/14/2020 9:22:49 AMADONE
follow up//permit is under review//
MIS20-00146 BLD-Conference5/7/20205/14/20205/14/2020 9:03:31 AMADONE
follow up on permits
MIS20-00146 DOC - Permit Finaled5/14/20205/14/20205/14/2020 9:03:20 AMPPASS
permit was issued for re-roof//
MIS18-00458 DOC - Permit Finaled5/14/20205/14/20205/14/2020 7:08:35 AMAPASS
old permit, no follow ups//closing out//
BLD20-00304 BLD-Final5/13/20205/14/20205/14/2020 12:00:00 AMPCANC
Mike Phone #: ###-#### // cancelled waiting to final ELE