PLM01-00840
| Final | 5/14/2001 | 5/15/2001 | 5/15/2001 12:00:00 AM | A | PASS |
|
|
###-####
|
PLM01-01518
| Plumbing Rough-in | 5/15/2001 | 5/15/2001 | 5/15/2001 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM01-00881
| Water and/or Sewer | 5/15/2001 | 5/15/2001 | 5/15/2001 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM01-01481
| Plumbing Rough-in | 5/15/2001 | 5/15/2001 | 5/15/2001 12:00:00 AM | P | FAIL |
|
|
Craig ###-#### not ready, tests not on 5/15/2001 2:57:40 PM
|
PLM01-01527
| Plumbing Rough-in | 5/15/2001 | 5/15/2001 | 5/15/2001 12:00:00 AM | P | PASS |
|
|
###-####
|
PLM01-00463
| Water and/or Sewer | 5/15/2001 | 5/15/2001 | 5/15/2001 12:00:00 AM | P | CANC |
|
|
Scheduled by Inspector: 309 On 5/15/2001 2:13:28 PM
|
PLM01-00463
| Final | 5/15/2001 | 5/15/2001 | 5/15/2001 12:00:00 AM | P | PASS |
|
|
Scheduled by Inspector: 309 On 5/15/2001 2:14:16 PM
|
PLM01-01510
| Sprinkler (Final) | 5/14/2001 | 5/15/2001 | 5/15/2000 12:00:00 AM | A | PASS |
|
|
###-####
|