Inspections for the day of: Thursday, May 15, 2008.
Number of inspections: 12
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJim Sly
TitleBLD-COM/RES INSPECTOR
Phone #794-9465
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD08-00113 BLD-Energy code compliance5/15/20085/15/20085/15/2008 4:58:30 PMPPASS
rob - insulation Phone #: ###-####
BLD08-00631 BLD-Framing/Rough-in5/15/20085/15/20085/15/2008 4:58:06 PMPPASS
mike Phone #: ###-####
BLD08-00672 BLD-Final5/14/20085/15/20085/15/2008 4:23:56 PMPPASS
doug Phone #: ###-####
c/c issued
BLD08-00672 DOC - Permit Finaled5/15/20085/15/20085/15/2008 4:23:33 PMPPASS
BLD08-00216 BLD-Energy code compliance5/15/20085/15/20085/15/2008 3:41:27 PMPPASS
curt - insulation - after 3:00 if possible Phone #: ###-####
BLD08-00983 BLD-Final5/13/20085/15/20085/15/2008 3:40:54 PMPPART
david Phone #: ###-####
OK for Temp Occ......OK for Perm Occ when Fire Corrections completed....and fire Perms.
MIS07-00203 BLD-Conference5/15/20085/15/20085/15/2008 2:45:09 PMPPEND
arty Phone #: ###-####
Will call for finals.....
BLD08-00594 BLD-Other5/14/20085/15/20085/15/2008 2:22:23 PMAPART
Threaded Rebar Inspection - Masonry Phone #: ###-#### Internet Inspection Request from: Jessica Noland
OK pending MTI special inspection....tests....and approvals.
BLD06-02489 BLD-Energy code compliance5/14/20085/15/20085/15/2008 11:36:39 AMAPART
mike - partial insulation Phone #: ###-#### East 1/3rd of Bldg OK to cover.
BLD07-02906 BLD-Conference5/14/20085/15/20085/15/2008 11:27:19 AMADONE
EXP




BLD07-02906 DOC - Permit Expired5/15/20085/15/20085/15/2008 11:26:01 AMPPASS
BLD07-01278 BLD-Framing/Rough-in5/13/20085/15/20085/15/2008 11:24:05 AMANR
ron Phone #: ###-####
Framing not per appr plan. Re-submit to PDS. Arch to provide UL assemblies for 1hr stair enclosure.