ELE10-01688
| ELE-Aging Inspection | 5/15/2013 | 5/15/2013 | 5/15/2013 2:33:16 PM | | DONE |
|
|
contractor will call for final
|
ELE10-01304
| ELE-Aging Inspection | 5/15/2013 | 5/15/2013 | 5/15/2013 2:27:39 PM | | DONE |
|
|
still under construction
|
ELE13-00646
| Final | 5/15/2013 | 5/15/2013 | 5/15/2013 2:25:25 PM | P | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Neal Rumsey final ok
|
ELE13-01215
| Conference | 5/15/2013 | 5/15/2013 | 5/15/2013 1:24:26 PM | P | DONE |
|
|
Call for access, will be out 2-4 - Jean Phone #: ###-#### Discussed requirements for replacing underground service raiser and resecuring service meter base
|
ELE13-00061
| Final | 5/14/2013 | 5/15/2013 | 5/15/2013 12:50:57 PM | P | PASS |
|
|
Please let me know if there are any problems. Thanks Phone #: ###-#### >> Inspection requested via web by Clay Morgan final ok
|
ELE12-02891
| ELE-Request for Extension | 5/15/2013 | 5/15/2013 | 5/15/2013 12:18:30 PM | P | DONE |
|
|
Richard Phone #: ###-#### Request for extension ok
|
ELE12-03040
| Final | 5/15/2013 | 5/15/2013 | 5/15/2013 10:39:40 AM | P | PASS |
|
|
Swimming Pool Electrical Phone #: ###-#### >> Inspection requested via web by Lars Johnson final ok
|
ELE12-03040
| Electrical Rough-In | 5/15/2013 | 5/15/2013 | 5/15/2013 10:38:52 AM | P | PASS |
|
|
Potting compound Phone #: ###-#### >> Inspection requested via web by Lars Johnson rough-in ok
|
ELE13-01210
| Final | 5/15/2013 | 5/15/2013 | 5/15/2013 10:37:54 AM | A | PASS |
|
|
Unattached garages,two locations final ok
|
ELE13-01210
| Final | 5/15/2013 | 5/15/2013 | 5/15/2013 10:37:17 AM | P | PASS |
|
|
Thank You!! Phone #: ###-#### >> Inspection requested via web by Tracy Robertson final ok
|
ELE13-01195
| Electrical Rough-In | 5/13/2013 | 5/15/2013 | 5/15/2013 10:27:51 AM | A | PASS |
|
|
Phone #: ###-#### >> Inspection requested via web by Henry Neddo lighting retro UL listed material, rough-in ok
|
ELE13-01211
| Final | 5/15/2013 | 5/15/2013 | 5/15/2013 9:47:24 AM | A | PASS |
|
|
job complete final ok
|
ELE13-01211
| Electrical Rough-In | 5/14/2013 | 5/15/2013 | 5/15/2013 9:44:53 AM | A | PASS |
|
|
Pulled a new circuit in an existing conduit from panel sp1 to a vehicle hoist Phone #: ###-#### >> Inspection requested via web by Matthew White rough-in ok
|
ELE13-00498
| Electrical Rough-In | 5/14/2013 | 5/15/2013 | 5/15/2013 9:16:32 AM | A | PASS |
|
|
Contact: Andy Eckhart - Breakroom ceiling & conference room walls, phase 2 Phone #: ###-#### >> Inspection requested via web by Deb Gooden rough-in ok cover
|
ELE12-03040
| Final | 5/14/2013 | 5/15/2013 | 5/15/2013 9:00:01 AM | A | FAIL |
|
|
Swiming pool electrical Phone #: ###-#### >> Inspection requested via web by Lars Johnson No record of potting pool luminaires
|
ELE13-01206
| Electrical Rough-In | 5/14/2013 | 5/15/2013 | 5/15/2013 8:33:11 AM | A | PASS |
|
|
underground inspection. call chris ###-#### or mike ###-#### Phone #: ###-#### >> Inspection requested via web by Cyndi Dale rough-in ok cover underground
|
ELE12-02406
| Final | 5/14/2013 | 5/15/2013 | 5/15/2013 8:17:34 AM | A | PASS |
|
|
Swimming pool/spa electrical Phone #: ###-#### >> Inspection requested via web by Lars Johnson final ok
|