Inspections for the day of: Wednesday, May 15, 2019.
Number of inspections: 5
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorChad Schwendiman
TitleMEC-INSPECTOR
Phone #780-9549
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC19-01826 Rough-in5/15/20195/15/20195/15/2019 3:10:24 PMPPASS
rough in Phone #: ###-#### Inspection requested via web by Brandon Sorensen - Need to address return air pathway prior to final
MEC18-04097 Final5/14/20195/15/20195/15/2019 2:22:29 PMPFAIL
Antonio is the contact Phone #: ###-#### Inspection requested via web by stan lillquist - Need a preliminary air balance report showing ventilation air for area to be occupied
MEC19-01256 Final5/14/20195/15/20195/15/2019 2:21:23 PMPPASS
Please contact Dustin at ###-#### before arriving and with any questions you may have. Thank you! Phone #: ###-#### Inspection requested via web by Rhonda Marcum
MEC18-05005 Final5/14/20195/15/20195/15/2019 11:19:27 AMAFAIL
Final for Pioneer Crossing - Please call Lou ###-#### Phone #: ###-#### Inspection requested via web by Heather Gransbery - Need uv protection on exposed arma flex, Need to remove sheetrock in front of duct heater access
MEC18-03012 Final5/14/20195/15/20195/15/2019 11:18:38 AMAFAIL
BRIAN IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER - Need to secure gas piping to support blocks on roof, need to seal gas pipe where it passes through exterior wall. Need to complete condensate piping on units