PLM03-01079
| Plumbing Rough-in | 5/15/2003 | 5/16/2003 | 5/16/2003 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 5/15/2003 at 4:22:04 PM. Contact: ###-####.
|
PLM03-01349
| Sprinkler (Final) | 5/15/2003 | 5/16/2003 | 5/16/2003 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 5/15/2003 at 4:44:33 PM. Contact: ###-####. tie in ok ok to cover contractor to recall when pvb has been certified 5/16/2003 10:42:15 AM
|
PLM03-01349
| Sprinkler (Final) | 5/15/2003 | 5/16/2003 | 5/16/2003 12:00:00 AM | A | PART |
|
|
cliffton harris ###-#### tie in ok ok to cover contractor to recall when pvb has been certified 5/16/2003 10:43:24 AM
|
PLM03-01005
| Plumbing Rough-in | 5/16/2003 | 5/16/2003 | 5/16/2003 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 5/16/2003 at 8:49:44 AM. Contact: ###-####.
|
PLM03-01020
| Water and/or Sewer | 5/16/2003 | 5/16/2003 | 5/16/2003 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 5/16/2003 at 9:14:31 AM. Contact: ###-####. spaces 18 & 20 sewer and hook-up ok 5/16/2003 2:28:28 PM
|
PLM03-01421
| Final | 5/16/2003 | 5/16/2003 | 5/16/2003 12:00:00 AM | P | PASS |
|
|
###-#### jim
|
PLM03-01423
| Water and/or Sewer | 5/16/2003 | 5/16/2003 | 5/16/2003 12:00:00 AM | P | PASS |
|
|
###-#### dj
|
PLM03-00689
| Final | 5/16/2003 | 5/16/2003 | 5/16/2003 12:00:00 AM | P | PASS |
|
|
|
PLM03-01187
| Plumbing Rough-in | 5/16/2003 | 5/16/2003 | 5/16/2003 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 5/16/2003 at 8:02:55 AM. Contact: ###-####.in wall piping for lav rough-in in rooms 503 through 506 test ok need to repipe under floor drain to shower in room 512 5/16/2003 3:55:36 PM
|
PLM03-01413
| Sprinkler (Final) | 5/15/2003 | 5/16/2003 | 5/16/2003 12:00:00 AM | P | PASS |
|
|
###-#### chad
|
PLM03-01414
| Sprinkler (Final) | 5/15/2003 | 5/16/2003 | 5/16/2003 12:00:00 AM | P | PASS |
|
|
###-#### chad
|