Inspections for the day of: Monday, May 16, 2016.
Number of inspections: 2
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy James
TitleMEC-COM/RES INSPECTOR
Phone #794-9461
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MEC16-02086 Rough-in5/16/20165/16/20165/16/2016 3:19:23 PMPPASS
light test inspection will be ready around 3 p.m. Phone #: ###-#### Inspection requested via web by Drew Tverdy
Found holes in the welds. Contractor fixed holes. Light test ok
MEC15-04552 Rough-in5/16/20165/16/20165/16/2016 3:01:05 PMPPASS
Hydrostatic Test - Roof ; Shaft (basement to 6th floor). if questions call Mike @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann
ok hot and chilled lines from basement to AH on roof to annex bldg