NAF17-00031
| INSP-Final | 5/16/2017 | 5/16/2017 | 5/16/2017 3:50:00 PM | P | PASS |
|
|
Paint Booth suppression system tested OK. Powder coating booth and industrial oven to be permitted and protected separately.
|
NAF17-00032
| INSP-Final | 5/16/2017 | 5/16/2017 | 5/16/2017 1:43:10 PM | P | PART |
|
|
Ok to cover. Crawl space and roof overbuild areas with sprinkler protection to be tented and have acive heat sourced from warehouse and office areas. Final inspection will occur after finish is installed in office areas.
|
NAF16-00084
| INSP-Sprinkler Rough-in/Hydro | 5/15/2017 | 5/16/2017 | 5/16/2017 1:30:30 PM | A | PART |
|
|
Rough toc cover PASS. Crawl space and overhead inspected. Overbuild sprinklers to be heated with active heating through transfer grills from warehouse and lower office combined with insulation tenting. Finish sheet rock needs to be installed prior to final inspection.
|