FIR10-00556
| INSP-Sprinkler Rough-in | 5/17/2011 | 5/17/2011 | 5/17/2011 3:18:39 PM | P | PASS |
|
|
The piping in two additional exam rooms and one restroom is ok to cover. See the city approved plans for the locations marked in red.
|
BLD10-01595
| FIRE-Final Inspection | 5/16/2011 | 5/17/2011 | 5/17/2011 2:36:26 PM | A | FAIL |
|
|
Provide vent within 6" of the ceiling, provide NFPA hazard sign and provide fire dept access signage as discussed.
|
FIR11-00027
| INSP-Final Inspection | 5/16/2011 | 5/17/2011 | 5/17/2011 1:45:03 PM | A | FAIL |
|
|
The underground supply was flushed but the permit could not be finaled due to possible sprinkler modifications required due to ceiling changes.
|
FIR11-00031
| INSP-Final Inspection | 5/16/2011 | 5/17/2011 | 5/17/2011 1:42:49 PM | A | CANC |
|
|
mike Phone #: ###-####
|