Inspections for the day of: Friday, May 18, 2001.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorJoe Tawney
TitleFIRE INSPECTOR
Phone #340-1295
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR01-00300 INSP-Supply line flush5/17/20015/18/20015/18/2001 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 05/17/2001 at 14:09:44. Contact: ###-####. Ok to cover Riser stub in to bldg 5/18/2001 10:52:21 AM
BLD01-00426 FIRE-Final Inspection5/17/20015/18/20015/18/2001 12:00:00 AMAFAIL
Greg ###-#### Final Fail C/N issued 5/18/2001 9:34:13 AM
FIR01-00122 INSP-Supply line flush5/17/20015/18/20015/18/2001 12:00:00 AMAPART
Scheduled by a contractor via Hello! on 05/17/2001 at 11:45:55. Contact: ###-####. OK on supply line flush 5/18/2001 12:56:30 PM
FIR01-00272 INSP-Alarm Testing5/17/20015/18/20015/18/2001 12:00:00 AMPFAIL
Scheduled by a contractor via Hello! on 05/17/2001 at 13:27:54. Contact: ###-####. Final Fail need correct size batteries 5/18/2001 2:06:47 PM
FIR01-00319 INSP-Sprinkler Rough-in5/18/20015/18/20015/18/2001 12:00:00 AMPPART
underground Becky ###-#### OK to cover supply line from riser to loop end 90 5/18/2001 3:19:28 PM
BLD01-00426 FIRE-Final Inspection5/18/20015/18/20015/18/2001 12:00:00 AMPFAIL
###-#### Reinsp Fail Access controlled exit doors 5/18/2001 4:46:22 PM
BLD01-00703 FIRE-Final Inspection5/18/20015/18/20015/18/2001 12:00:00 AMPPASS
###-#### reinspection REinsp OK for permanant occupancy 5/18/2001 2:20:59 PM
BLD00-03631 BLD-Final5/18/20015/18/20015/18/2001 12:00:00 AMPFAIL
Added by Inspector: 406 On 5/18/2001 2:12:10 PM Reinsp Fail Fire door and batteries in FACP, Knox Box, breaker lock for FACP