FIR06-00140
| INSP-Final Inspection | 5/16/2006 | 5/18/2006 | 5/18/2006 4:03:12 PM | P | PART |
|
|
Fire sprinkler for the west half of the remodel area under the scope of work passed final inspection.
|
FIR06-00285
| INSP-Sprinkler Rough-in | 5/17/2006 | 5/18/2006 | 5/18/2006 3:14:21 PM | P | PART |
|
|
Overhead sprinkler rough-in inspection for cover is satisfactory except one room at the NW corner which is overspaced per design limitations, also need to provide plans reflecting changed wall locations and added/deleted heads at various locations where different from approved drawings.
|
FIR06-00199
| INSP-Final Inspection | 5/17/2006 | 5/18/2006 | 5/18/2006 2:40:41 PM | P | PART |
|
|
Fire alarm testing for the area of remodel designated as phase one is acceptable as marked on approved plans, one duct detector has the sample and vent tubes installed backward, need to test the manual pull at the nurses station, will verify these items at next inspection for the remainder of the project scope.
|
BLD06-00317
| FIRE-Final Inspection | 5/17/2006 | 5/18/2006 | 5/18/2006 11:01:50 AM | A | PART |
|
|
Life safety inspection for the west half of the floor remodel is acceptable.
|
FIR06-00258
| INSP-Alarm Testing | 5/15/2006 | 5/18/2006 | 5/18/2006 11:00:28 AM | A | PART |
|
|
Alarm tested satisfactory for the west portion of the project, need to add one notification device at area lacking coverage as marked on approved plans, the remainder of alarm work for the east half of the floor is not yet completed.
|
FIR06-00331
| INSP-Final Inspection | 5/16/2006 | 5/18/2006 | 5/18/2006 9:20:18 AM | A | FAIL |
|
|
Electrical power failed to shut down upon activation of the hood suppression system, "blow off" test and the manual pull tested satisfactory. Need to relocate the K class extinguisher a min. of 10' feet from the cooking appliances.
|