BLD10-00763
| FIRE-Conference | 5/18/2010 | 5/18/2010 | 5/18/2010 5:25:17 PM | P | DONE |
|
|
Regarding site work in progress.
|
BLD09-02206
| FIRE-Final Inspection | 5/18/2010 | 5/18/2010 | 5/18/2010 5:23:24 PM | P | PASS |
|
|
Listed corrections per site visit 1/19 verified for compliance. Fire life safety finaled.
|
FIR10-00100
| INSP-Supply line flush | 5/18/2010 | 5/18/2010 | 5/18/2010 5:20:20 PM | P | PART |
|
|
Underground fire supply line flush completed satisfactory.
|
BLD10-00539
| FIRE-Final Inspection | 5/17/2010 | 5/18/2010 | 5/18/2010 5:18:32 PM | A | PASS |
|
|
Noted items on previous correction list verified for completion, inspection passed.
|
FIR05-00321
| DOC - Permit Expired | 5/18/2010 | 5/18/2010 | 5/18/2010 5:17:16 PM | A | PASS |
|
|
|
FIR05-00172
| INSP-Final Inspection | 5/18/2010 | 5/18/2010 | 5/18/2010 5:14:56 PM | A | PASS |
|
|
Permit approved for final status- see project related FIR05-00202- fire alarm interconnect completed.
|
FIR09-00536
| INSP-Sprinkler Rough-in | 5/17/2010 | 5/18/2010 | 5/18/2010 5:10:46 PM | A | PART |
|
|
Overhead install at the first floor approved for cover per annotations on stamped plan set marked with today's date with the exception of stair 127 not yet finished. Also noted head guards to be provided for upright heads at the gym.
|
BLD08-00264
| FIRE-Final Inspection | 5/18/2010 | 5/18/2010 | | P | |
|
|
Jim phone #: ###-####
|