BLD09-01611
| FIRE-Final Inspection | 5/17/2010 | 5/18/2010 | 5/19/2010 8:50:31 AM | A | FAIL |
|
|
Could not final permit due to a new fire hydrant being shown not only on sheet ADD on this permit but also on the phase I drawings sheet F-1. The hydrant has not been installed. I spoke to scott arellano and he stated that the hydrant is not required but plans sheets will need to be resubmitted showing the fire hydrant removed for both permits. I let Mike the job superintendant know. The other option is to install the fire hydrant.
|
BLD10-00661
| FIRE-Conference | 5/17/2010 | 5/18/2010 | 5/19/2010 6:48:03 AM | P | CANC |
|
|
Marvin Phone ###-####
|
BLD09-00945
| FIRE-Final Inspection | 5/18/2010 | 5/18/2010 | 5/18/2010 2:46:51 PM | P | FAIL |
|
|
Todays inspection was for phase 9. Two exit signs need to be added as discussed. The missing exit sign in the short corridor at restroom 118 can remain missing. This work will be completed by morning per Darren. A follow up inspection has been scheduled.
|
FIR10-00225
| INSP-Alarm Testing | 5/18/2010 | 5/18/2010 | 5/18/2010 2:44:50 PM | P | PASS |
|
|
The phase 9 fire alarm testing is complete.
|
FIR10-00192
| INSP-Conference | 5/18/2010 | 5/18/2010 | 5/18/2010 2:35:24 PM | P | DONE |
|
|
Corrdinated with mark to meet just after 7:00am
|
FIR10-00134
| INSP-Conference | 5/18/2010 | 5/18/2010 | 5/18/2010 2:35:01 PM | P | DONE |
|
|
Corrdinated with mark to meet just after 7:00am
|
FIR10-00133
| INSP-Conference | 5/18/2010 | 5/18/2010 | 5/18/2010 2:34:42 PM | P | DONE |
|
|
Corrdinated with mark to meet just after 7:00am
|
FIR10-00132
| INSP-Conference | 5/18/2010 | 5/18/2010 | 5/18/2010 2:34:03 PM | P | DONE |
|
|
Corrdinated with mark to meet just after 7:00am
|
BLD09-02069
| FIRE-Final Inspection | 5/18/2010 | 5/18/2010 | 5/18/2010 2:32:44 PM | P | PART |
|
|
The life safety for phase two passed.
|
FIR10-00032
| INSP-Final Inspection | 5/18/2010 | 5/18/2010 | 5/18/2010 2:32:19 PM | P | PASS |
|
|
The fire sprinkler work in phase two passed inspection
|
FIR10-00073
| INSP-Sprinkler Rough-in | 5/14/2010 | 5/18/2010 | 5/18/2010 2:31:41 PM | A | PASS |
|
|
The fire alarm in phase two passed inspection
|
FIR10-00217
| INSP-Final Inspection | 5/17/2010 | 5/18/2010 | 5/18/2010 2:31:11 PM | A | PASS |
|
|
Permit finaled
|
BLD10-00383
| FIRE-Final Inspection | 5/17/2010 | 5/18/2010 | 5/18/2010 10:05:38 AM | A | PART |
|
|
A temporary occupancy was given with Steve Keiters permission until the third exit that was to be infilled is provided with approved single action hardware.
|
FIR10-00016
| INSP-Final Inspection | 5/17/2010 | 5/18/2010 | 5/18/2010 10:04:24 AM | A | PASS |
|
|
Permit finaled. The originally submitted model of panel has been installed. The Netcon for this panel was a 5 as well.
|