Inspections for the day of: Friday, May 19, 2006.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR05-00788 INSP-Sprinkler Rough-in/Hydro5/19/20065/19/20065/19/2006 5:23:31 PMPCANC
No time for inspection. Will need to be rescheduled.
BLD05-00928 FIRE-Final Inspection5/19/20065/19/20065/19/2006 5:22:53 PMPFAIL
Provide blank instead of the keyed lock on the exterior door.
BLD05-03448 FIRE-Conference5/12/20065/19/20065/19/2006 5:21:01 PMPCANC
Per the contractor this conference had been canceled earlier.
BLD06-00323 FIRE-Final Inspection5/18/20065/19/20065/19/2006 3:29:19 PMAPART
A temporary occupancy was given, same as on the 5th floor until the permanant emergency light fixtures are installed.
FIR06-00285 INSP-Final Inspection5/19/20065/19/20065/19/2006 3:26:23 PMPPASS
Permit finaled. Two additional heads were required in the conference room. The installation of these heads was verified by dave hanna.
BLD05-02880 FIRE-Final Inspection5/19/20065/19/20065/19/2006 3:10:41 PMPFAIL
Plan review comments had not been followed as far as providing verification of the existing sprinkler systems design parameters. No real inspection done. Just went over what I will need for the next inspection.
BLD05-02650 FIRE-Conference5/18/20065/19/20065/19/2006 3:08:57 PMADONE
I went over life safety items with Darren. Needs address on both corners of the building and to test the exit discharge lighting when complete.
BLD04-00709 FIRE-Final Inspection5/18/20065/19/20065/19/2006 1:48:08 PMPPASS
life safety finaled
BLD06-01112 FIRE-Final Inspection5/18/20065/19/20065/19/2006 1:12:33 PMPPASS
Life safety finaled. The contractor was installing the lever passage hardware on the new door as I left.
BLD05-00347 FIRE-Final Inspection5/18/20065/19/20065/19/2006 12:58:17 PMPFAIL
Contractor intended for the inspection to be for the associated racking permit, BLD05-02880, but I went over the outstanding issues for this permit with him. Dereck stated he would followup on all items and get it finaled. The associated fire alarm permit is not finaled either.
BLD05-03376 FIRE-Final Inspection5/19/20065/19/20065/19/2006 11:24:42 AMPPASS
Life safety finaled.
FIR06-00264 INSP-Final Inspection5/18/20065/19/20065/19/2006 11:00:54 AMACANC
Wrong permit called in. Inspection was ment for suite 610
FIR06-00265 INSP-Final Inspection5/19/20065/19/20065/19/2006 11:00:18 AMPPASS
Permit finaled
FIR05-00496 INSP-Final Inspection5/18/20065/19/20065/19/2006 10:58:16 AMAPASS
Permit finaled
BLD05-03401 FIRE-Final Inspection5/18/20065/19/20065/19/2006 10:57:43 AMAPASS
Life safety finaled
FIR05-00864 INSP-Final Inspection5/18/20065/19/20065/19/2006 10:57:25 AMAPASS
Permit finaled
FIR05-00495 INSP-Final Inspection5/18/20065/19/20065/19/2006 8:53:35 AMAPASS
Permit finaled
FIR05-00494 INSP-Final Inspection5/18/20065/19/20065/19/2006 8:47:52 AMAPASS
Permit finaled