ELE10-01638
| ELE-Aging Inspection | 5/19/2016 | 5/19/2016 | 5/20/2016 3:27:30 PM | | CANC |
|
|
|
ELE16-00521
| Electrical Rough-In | 5/19/2016 | 5/19/2016 | 5/19/2016 4:10:19 PM | P | PASS |
|
|
For sign on front of building. Chris is the contact his cell is ###-#### Phone #: ###-#### Inspection requested via web by Shawna Gates Stub out for sign rough in ok cover
|
ELE16-00329
| Final | 5/19/2016 | 5/19/2016 | 5/19/2016 3:48:13 PM | P | NR |
|
|
Partial - Floors 5 ; 6 Only Roger Bachman Phone #: ###-#### Inspection requested via web by Kerri Hamilton Pre walk to cover most of floors noted. Bath outlet not GFCI protected, 5th floor electrical rm ground listed splice needed. 4 sq cover and ko seal. furniture on sight will be wired rest to be covered under seperate permit.
|
ELE16-01041
| Conference | 5/18/2016 | 5/19/2016 | 5/19/2016 2:14:55 PM | P | DONE |
|
|
Adam-please call with an estimated meet time Phone #: ###-#### Owner did not have questions informed of secure, support, tamper resistant, dedicated circuit for garage spaces, and GFCI protection. Old wiring on house warm wall not going to be touched or change.
|
ELE13-01291
| Electrical Rough-In | 5/18/2016 | 5/19/2016 | 5/19/2016 1:03:44 PM | P | PASS |
|
|
Rough in for northeast site underground. Contact Frank Yantis Phone #: ###-#### Inspection requested via web by Tony Keen N.W. corner planter and sidewalk underground rough in ok cover
|
ELE15-01348
| Electrical Rough-In | 5/18/2016 | 5/19/2016 | 5/19/2016 12:51:42 PM | A | NH |
|
|
Lvl 6 Bathroom Ceilings Phone #: ###-#### Inspection requested via web by Tom Betty Tryed to call contact number, no answer, message said no voicemail set up yet. recall
|
ELE15-03901
| Conference | 5/18/2016 | 5/19/2016 | 5/19/2016 11:58:23 AM | A | DONE |
|
|
Walk through to review project progress. Phone #: ###-#### Inspection requested via web by Rafael Castillo Met and walked 5, 6, 7 to get caught up on jb progress. Still HVAC units with clearence issue at junction box.
|
ELE16-00089
| Electrical Rough-In | 5/18/2016 | 5/19/2016 | 5/19/2016 11:27:06 AM | A | PASS |
|
|
Walk through to review project progress. R/I inspection of bathrooms on south end of 4th floor area C. Phone #: ###-#### Inspection requested via web by Rafael Castillo Area noted baths wall rough only ok cover
|
ELE16-01594
| Conference | 5/18/2016 | 5/19/2016 | 5/19/2016 9:59:54 AM | A | DONE |
|
|
please call Greg Critchfield at ###-#### to meet with him (or to find him). St. Al''s Hospital. Phone #: ###-#### Inspection requested via web by Debby Pierce All previous notes on permit ELE12-00802. Discussed associated fire pump and controller location and wiring. Spec sheet provided for 2 hour fire resistant conductors RHW-2 to be used.
|
ELE16-01602
| Electrical Rough-In | 5/18/2016 | 5/19/2016 | 5/19/2016 8:38:29 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Don Conley Basement rough in ok cover
|
ELE16-01838
| Electrical Rough-In | 5/19/2016 | 5/19/2016 | 5/19/2016 12:00:00 AM | P | PASS |
|
|
Still in area so drove back by. 2nd floor south office walls 233 thru 237 walls and 6th floor bathroom ceilings rough in ok cover.
|