BLD20-01463
| BLD-Footing | 5/19/2020 | 5/19/2020 | 5/21/2020 1:20:32 PM | P | DONE |
|
|
An early PM inspection would be great for this inspection. Alex will be doing the installation and his cell number is ###-####. Thanks. Phone #: ###-#### Inspection requested via web by rich prasch
|
BLD19-04974
| BLD-Energy code compliance | 5/19/2020 | 5/19/2020 | 5/20/2020 10:07:36 AM | P | DONE |
|
|
screened // James Phone #: ###-####
|
BLD19-03665
| BLD-Final | 5/19/2020 | 5/19/2020 | 5/19/2020 5:37:17 PM | P | PASS |
|
|
Steve Phone #: ###-####
|
BLD19-03665
| DOC - Permit Finaled | 5/19/2020 | 5/19/2020 | 5/19/2020 5:37:07 PM | P | PASS |
|
|
|
BLD20-00760
| BLD-Framing/Rough-in | 5/19/2020 | 5/19/2020 | 5/19/2020 5:36:46 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Tiffany Cushing
|
BLD19-03665
| DOC - Permit Finaled | 5/19/2020 | 5/19/2020 | 5/19/2020 2:37:48 PM | P | PASS |
|
|
|
BLD19-04543
| BLD-Framing/Rough-in | 5/15/2020 | 5/19/2020 | 5/19/2020 12:58:23 PM | P | PART |
|
|
call access- Ashley *screened* Phone #: ###-#### roof truss ok replacment wall framing and headers ok still needs all rought ins done
|
BLD20-00061
| BLD-Concrete | 5/18/2020 | 5/19/2020 | 5/19/2020 11:51:49 AM | A | PASS |
|
|
basement walls-Tony *screened* Phone #: ###-####
|
BLD18-00357
| BLD-Conference | 5/15/2020 | 5/19/2020 | 5/19/2020 11:51:36 AM | A | DONE |
|
|
Status any change? almost finished
|
BLD19-00472
| BLD-Conference | 5/15/2020 | 5/19/2020 | 5/19/2020 9:24:47 AM | A | DONE |
|
|
Status? ext of project is done
|
BLD18-01831
| BLD-Wall cover | 5/18/2020 | 5/19/2020 | 5/19/2020 9:24:47 AM | A | PASS |
|
|
Third floor Framing, Front Street. Recap and Review EJ for plumbing assemblies. Possibly review shafts at other areas if complete. Call Adam when heading to site. Thanks. AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson Phone #: ###-#### Inspection requested via web by Adam Johnson
|