MEC02-01181
| Pressure Test | 5/1/2002 | 5/2/2002 | 5/2/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 05/01/2002 at 15:23:18. Contact: ###-####.. from meter along pl line to pool heater. 5/2/2002 11:30:55 AM
|
BLD02-00475
| BLD-Final | 5/1/2002 | 5/2/2002 | 5/2/2002 12:00:00 AM | A | PASS |
|
|
Don, ###-#### Ok perm oc. 5/2/2002 11:17:00 AM
|
BLD02-00540
| BLD-Footing | 5/2/2002 | 5/2/2002 | 5/2/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 05/02/2002 at 06:30:31. Contact: ###-####.
|
BLD02-00540
| BLD-Footing | 5/2/2002 | 5/2/2002 | 5/2/2002 12:00:00 AM | A | PART |
|
|
Scheduled by a contractor via Hello! on 05/02/2002 at 06:30:31. Contact: ###-####.
|
BLD01-02612
| BLD-Framing/Rough-in | 5/1/2002 | 5/2/2002 | 5/2/2002 12:00:00 AM | A | PART |
|
|
Scheduled by Inspector: 407 On 5/1/2002 1:45:08 PM ok to cover lid in exterior canopy ok . 5/2/2002 12:08:27 PM
|
BLD01-02963
| BLD-Footing | 5/1/2002 | 5/2/2002 | 5/2/2002 12:00:00 AM | A | PART |
|
|
###-#### BRENT . Office ok , screen wall needs verticals inplace will recall. 5/2/2002 10:31:09 AM
|
BLD01-02802
| BLD-Framing/Rough-in | 5/1/2002 | 5/2/2002 | 5/2/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 05/01/2002 at 14:31:11. Contact: ###-####. Need approval from engineer for wall connections at front entry framing agains 5/2/2002 4:29:39 PM t cmu wall , no c/n as was not complete.5/2/2002 4:29:49 PM 5/2/2002 4:30:12 PM
|
BLD02-01001
| BLD-Framing/Rough-in | 4/26/2002 | 5/2/2002 | 5/2/2002 12:00:00 AM | P | PART |
|
|
late pm Kenny ###-#### New roof trusses are in place, The cmu wall to top cord of truss straps are not in place, also roof nailing not yet complete, will recall for am. 5/2/2002 4:35:41 PM 5/2/2002 4:36:52 PM
|
BLD01-01778
| BLD-Foundation | 5/2/2002 | 5/2/2002 | 5/2/2002 12:00:00 AM | P | PASS |
|
|
###-#### JED wall 5/2/2002 4:28:32 PM 5/2/2002 4:28:46 PM
|