Inspections for the day of: Monday, May 2, 2005.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorDave Hannah
TitleBLD-COM/RES INSPECTOR
Phone #794-1967
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD03-01830 BLD-Aging Inspection5/2/20055/2/20055/3/2005 11:49:18 AM PASS
work in progress
BLD03-01425 BLD-Aging Inspection5/2/20055/2/20055/3/2005 9:34:04 AM PASS
BLD05-00966 BLD-Foundation5/2/20055/2/20055/2/2005 4:18:40 PMPPART
Scheduled by a contractor via Hello! on 5/2/2005 at 7:36:15 AM. Contact: ###-####.
BLD05-00514 BLD-Foundation5/2/20055/2/20055/2/2005 4:17:58 PMPPART
Scheduled by a contractor via Hello! on 5/2/2005 at 7:37:08 AM. Contact: ###-####.
BLD05-00513 BLD-Framing/Rough-in5/2/20055/2/20055/2/2005 4:17:02 PMPNR
rob; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie no elec r/i no seal package no plans
BLD04-01323 BLD-Framing/Rough-in5/2/20055/2/20055/2/2005 3:23:34 PMPPART
Core wall framing inspection. Internet Inspection Request from: Alex Monge ok to cover walls on ext gaage side
BLD05-00102 BLD-Final5/2/20055/2/20055/2/2005 2:34:28 PMPPASS
Scheduled by a contractor via Hello! on 5/2/2005 at 11:21:06 AM. Contact: ###-####. ok for prem occ
BLD03-01830 BLD-Framing/Rough-in5/2/20055/2/20055/2/2005 2:01:10 PMPPART
paul///ceiling inspection on 1st floor lobby only please; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ceiling grid is org so its ok but need to patch holes in stair tower and elev shaft above ceiling line
BLD04-02482 BLD-Framing/Rough-in4/29/20055/2/20055/2/2005 1:49:41 PMAPASS
re-bar for pool///todd; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
BLD05-00077 BLD-Energy code compliance4/29/20055/2/20055/2/2005 9:31:34 AMAPASS
GARY; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to cover