ELE11-01094
| ELE-Aging Inspection | 5/2/2018 | 5/2/2018 | 5/3/2018 12:43:50 PM | | DONE |
|
|
waiting on permit holder...multiple attempts made
|
ELE18-01199
| Electrical Rough-In | 5/2/2018 | 5/2/2018 | 5/2/2018 2:27:14 PM | P | PASS |
|
|
Please call ahead for access - Ben Phone #: ###-####...ok to cover of open walls for kitchen wiring and new sub panel...3 breakers need changed to 2 pole for eddison circuit requirement by final
|
ELE18-01530
| Electrical Rough-In | 5/1/2018 | 5/2/2018 | 5/2/2018 1:31:05 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by BRS Permitting...UL listed equipment verified...40A breaker installed and labelled in panel
|
ELE18-00408
| Permanent Service | 5/2/2018 | 5/2/2018 | 5/2/2018 12:48:06 PM | P | NR |
|
|
Dustin is the site contact. Thank you! Phone #: ###-#### Inspection requested via web by Stacie Tasker...not ready...rescheduled to next day
|
ELE18-01656
| Final | 5/2/2018 | 5/2/2018 | 5/2/2018 12:42:27 PM | P | PASS |
|
|
rough in on LED kits for poles Phone #: ###-#### Inspection requested via web by Tim Dunlop...3 poles double heads...ok to final
|
ELE18-01656
| Electrical Rough-In | 5/2/2018 | 5/2/2018 | 5/2/2018 12:41:40 PM | P | PASS |
|
|
rough in on LED kits for poles Phone #: ###-#### Inspection requested via web by Tim Dunlop...UL listed equipment verified...driver and lamp kit
|
ELE18-01132
| Final | 5/2/2018 | 5/2/2018 | 5/2/2018 12:01:22 PM | P | PASS |
|
|
Early in the PM if possible. Contact: Jay Karel Phone #: ###-#### Inspection requested via web by Laurie Hoelscher...ok to final
|
ELE18-01132
| Electrical Rough-In | 5/2/2018 | 5/2/2018 | 5/2/2018 12:01:04 PM | P | PASS |
|
|
Early in the PM if possible. Contact: Jay Karel Phone #: ###-#### Inspection requested via web by Laurie Hoelscher...UL listing and disconnect verified...permit for sign only...electrician will need to be hired for power
|
ELE17-04255
| Final | 5/1/2018 | 5/2/2018 | 5/2/2018 11:31:29 AM | A | PASS |
|
|
garage code 0813 Phone #: ###-#### Inspection requested via web by cal crosby..corrections made..ok to final
|
ELE18-01525
| Final | 5/1/2018 | 5/2/2018 | 5/2/2018 10:17:30 AM | A | PASS |
|
|
ready for final Phone #: ###-#### Inspection requested via web by kyle carson...ok to final
|
ELE18-01653
| Permanent Service | 5/1/2018 | 5/2/2018 | 5/2/2018 10:16:57 AM | A | PASS |
|
|
new single wide trailer Phone #: ###-#### Inspection requested via web by kyle carson...p/s u/g new ok
|
ELE18-01146
| Final | 5/1/2018 | 5/2/2018 | 5/2/2018 9:19:52 AM | A | FAIL |
|
|
Karrigan Hollins, tech Phone #: ###-#### Inspection requested via web by BRS Permitting..1) breaker in panel needs correct labelling..2) wires in disconnect need installed correctly..all strands shall be properly installed underlugs..110.3
|
ELE18-01152
| Final | 5/1/2018 | 5/2/2018 | 5/2/2018 8:50:35 AM | A | PASS |
|
|
Karrigan Hollins, tech Phone #: ###-#### Inspection requested via web by BRS Permitting..labelling, disconnect and OCPD ok
|
ELE13-01262
| ELE-Aging Inspection | 5/2/2018 | 5/2/2018 | 5/2/2018 8:33:38 AM | | DONE |
|
|
waiting on contractor
|