BLD02-00526
| BLD-Energy code compliance | 5/17/2002 | 5/20/2002 | 5/20/2002 12:00:00 AM | A | FAIL |
|
|
Scheduled by a contractor via Hello! on 05/17/2002 at 09:44:30. Contact: ###-####. C/N--Prior c/n items not done. 5/20/2002 11:41:21 AM
|
MEC02-01341
| Rough-in | 5/17/2002 | 5/20/2002 | 5/20/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 05/17/2002 at 13:09:37. Contact: ###-####.
|
MEC02-01345
| Rough-in | 5/17/2002 | 5/20/2002 | 5/20/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 05/17/2002 at 14:22:41. Contact: ###-####.
|
MEC02-01345
| Pressure Test | 5/17/2002 | 5/20/2002 | 5/20/2002 12:00:00 AM | A | PASS |
|
|
Scheduled by a contractor via Hello! on 05/17/2002 at 14:23:04. Contact: ###-####.
|
BLD01-01641
| BLD-Framing/Rough-in | 5/17/2002 | 5/20/2002 | 5/20/2002 12:00:00 AM | P | FAIL |
|
|
###-#### C/N issued. Nail above hd, nailing light per plans at misc. locations. 5/20/2002 4:21:58 PM
|
BLD02-00613
| BLD-Wall cover | 5/20/2002 | 5/20/2002 | 5/20/2002 12:00:00 AM | P | PASS |
|
|
Scheduled by a contractor via Hello! on 05/20/2002 at 07:58:05. Contact: .
|
BLD02-00993
| BLD-Footing | 5/20/2002 | 5/20/2002 | 5/20/2002 12:00:00 AM | P | PART |
|
|
###-#### wip 5/20/2002 1:48:05 PM
|
BLD01-03038
| BLD-Framing/Rough-in | 5/20/2002 | 5/20/2002 | 5/20/2002 12:00:00 AM | P | PASS |
|
|
fr ted- ###-#### Ok to insulate. 5/20/2002 3:02:10 PM
|
BLD02-00821
| BLD-Other | 5/17/2002 | 5/20/2002 | 5/20/2002 12:00:00 AM | P | PART |
|
|
Scheduled by a contractor via Hello! on 05/17/2002 at 13:51:20. Contact: ###-####. SHEAR- Ext. shear ok--need interior shear inspection prior to mud and tape. 5/20/2002 3:12:44 PM
|
BLD02-00446
| BLD-Final | 5/17/2002 | 5/20/2002 | 5/20/2002 12:00:00 AM | P | CANC |
|
|
###-####--cancel per jennifer
|