ESC13-01009
| Aging Inspection | 5/20/2014 | 5/20/2014 | 5/20/2014 3:17:42 PM | | PASS |
|
|
Ongoing. No ESC Issues at time of inspection
|
ESC11-00192
| General Inspection | 5/20/2014 | 5/20/2014 | 5/20/2014 2:53:26 PM | | PASS |
|
|
No ESC Issues at time of inspetion
|
ESC13-00193
| General Inspection | 5/20/2014 | 5/20/2014 | 5/20/2014 2:40:35 PM | | PASS |
|
|
Only ESC Issue; Site Map shows a catch basin/ditch that runs along the entire south side of new phase from Crestline Rd. to the present catch basin/ditch down along the south side of phase 3 to tie into existing. Called Cameron and left VM disclosing this issue, and gave him till our next inspection (2 Weeks) to address issue (Due to Dry Season) to install this drainage ditch or stop work order will be issued to get back into compliance with their SWPPP Plan.
|