Inspections for the day of: Friday, May 20, 2016.
Number of inspections: 10
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR16-00282 INSP-Sprinkler Rough-in5/19/20165/20/20165/20/2016 2:16:38 PMPPASS
The North half for the first and second floors rough-in passed and the piping can be covered. I also inspected the north half fo the third floor but it did not pass because no tenting had been performed and there are pipe routing changes and additional fittings and added heads that will need to be reviewed prior to a cover inspection being approved.
NAF15-00043 INSP-Final5/19/20165/20/20165/20/2016 1:47:51 PMPPASS
Permit finaled
BLD16-00159 FIRE-Final Inspection5/20/20165/20/20165/20/2016 1:47:01 PMPPASS
Life safety passed
FIR16-00304 INSP-Final Inspection5/20/20165/20/20165/20/2016 12:34:36 PMPPASS
Permit finaled
NAF15-00043 INSP-Sprinkler Rough-in/Hydro5/19/20165/20/20165/20/2016 12:16:20 PMPPASS
Overhead hydro passed
FIR16-00303 INSP-Sprinkler Rough-in/Hydro5/19/20165/20/20165/20/2016 12:14:27 PMAPASS
Rough-in passed. Piping can be covered. Per Tim the two heads off of 1" outlet is approved
FIR16-00278 INSP-Final Inspection5/19/20165/20/20165/20/2016 12:13:37 PMAPASS
Permit finaled
FIR15-00822 INSP-Sprinkler Rough-in/Hydro5/20/20165/20/20165/20/2016 10:17:17 AMPCANC
Mark Jensen is the contact - ###-#### - would like a Hydro test this afternoon.
Thank you Phone #: ###-#### >> Inspection requested via web by Kay Haney Inspection cancelled from web by: Stan Beus
BLD16-00159 FIRE-Final Inspection5/19/20165/20/20165/20/2016 8:23:06 AMAFAIL
Missing a sprinkler canopy and the ceiling in the closet near the restrooms.
FIR16-00226 INSP-Sprinkler Rough-in5/19/20165/20/20165/20/2016 7:55:40 AMAPASS
Remaining piping can be covered