BLD13-03560
| FIRE-Final Inspection | 5/21/2014 | 5/21/2014 | 5/21/2014 3:05:42 PM | P | FAIL |
|
|
Provide current inspection tag for the fire extinguisher.
|
BLD13-00131
| FIRE-Final Inspection | 5/21/2014 | 5/21/2014 | 5/21/2014 3:04:23 PM | P | PASS |
|
|
Life safety passed
|
BLD14-00604
| FIRE-Conference | 5/21/2014 | 5/21/2014 | 5/21/2014 3:03:56 PM | P | DONE |
|
|
I spoke with Ami on the phone, from the project site, about the apparent need for fire alarm notification modifications due to wall changes. She would like me to meet with scott tomorrow.
|
FIR14-00294
| INSP-Sprinkler Rough-in | 5/20/2014 | 5/21/2014 | 5/21/2014 2:26:55 PM | A | PASS |
|
|
Piping is ok to cover. No walls have been built at this point so final pendant spacing will need to verified prior to a final sign off.
|
FIR06-00062
| FIR-Aging Inspection | 5/21/2014 | 5/21/2014 | 5/21/2014 1:15:17 PM | | NR |
|
|
General fire is out of business. I have spoken to Mary at Taylor Brothers about the need to schedule this and other out standing inspections.
|
FIR14-00155
| INSP-Sprinkler Rough-in/Hydro | 5/20/2014 | 5/21/2014 | 5/21/2014 1:14:16 PM | A | PASS |
|
|
The remaining overhead rough-in passed and all ceiling tile is ok to install. Also the overhead hydro test passed.
|
FIR14-00287
| INSP-Sprinkler Rough-in | 5/20/2014 | 5/21/2014 | 5/21/2014 10:42:46 AM | A | PASS |
|
|
Underground supply line is ok to cover.
|
FIR14-00296
| INSP-Sprinkler Rough-in | 5/20/2014 | 5/21/2014 | 5/21/2014 10:42:14 AM | A | PASS |
|
|
Underground supply line is ok to cover.
|
FIR14-00190
| INSP-Final Inspection | 5/20/2014 | 5/21/2014 | 5/21/2014 10:41:20 AM | A | PASS |
|
|
Permit finaled
|