ELE18-01833
| Electrical Rough-In | 5/21/2018 | 5/21/2018 | 5/21/2018 3:17:00 PM | P | PASS |
|
|
uNDERGROUND Phone #: ###-#### Inspection requested via web by Tom Jenkins u/g for parking lot ok to cover
|
ELE18-01808
| Electrical Rough-In | 5/17/2018 | 5/21/2018 | 5/21/2018 1:30:12 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Christy Cheney Corrections fixed ok to cover p/s u/g n ok
|
ELE17-02307
| Electrical Rough-In | 5/21/2018 | 5/21/2018 | 5/21/2018 1:29:36 PM | P | PASS |
|
|
Master bath floor heat. Phone #: ###-#### Inspection requested via web by Garrett Collins Master floor heat ok to cover
|
ELE18-01887
| Electrical Rough-In | 5/18/2018 | 5/21/2018 | 5/21/2018 10:24:26 AM | A | PASS |
|
|
groundwork- Bob Phone #: ###-#### Floor box for front of building ok to cover
|
ELE18-01784
| Rough-In Permanent Service | 5/18/2018 | 5/21/2018 | 5/21/2018 9:22:17 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Darryn Coburn Rough-in ok to cover p/s u/g n ok
|
ELE18-01665
| Final | 5/18/2018 | 5/21/2018 | 5/21/2018 9:21:30 AM | A | PASS |
|
|
Install wall signs reading Cirrus Aircraft Service Center on Northwest side of Maintenance building. All Primary power by others. Phone #: ###-#### Inspection requested via web by Ken Olsen Sign final ok
|
ELE18-01665
| Electrical Rough-In | 5/18/2018 | 5/21/2018 | 5/21/2018 9:20:56 AM | A | PASS |
|
|
Install wall signs reading Cirrus Aircraft Service Center on Northwest side of Maintenance building. All Primary power by others. Phone #: ###-#### Inspection requested via web by Ken Olsen Sign rough-in ok
|