Inspections for the day of: Thursday, May 22, 2008.
Number of inspections: 8
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorForrest France
TitleFIRE INSPECTOR
Phone #794-1981
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR07-00702 INSP-Sprinkler Rough-in5/21/20085/22/20085/22/2008 5:12:55 PMAPART
See areas red-lined on plan set for ceiling cover approved, field tile is not to be installed prior to rough-in inspection at the remainder of project remodel.
BLD07-02932 FIRE-Final Inspection5/21/20085/22/20085/22/2008 5:10:22 PMAFAIL
Several items noted including exit aisles at the north warehouse area are blocked by product storage, one ESFR head is obstructed by a roof drain, missing fire dept. key box, need to repair two exit signs, missing fire door signage and max occupant signage, need to post building address, missing doors at the new vestibule, three heads at the office area are out of adjustment, missing discharge light at the south office exit, need additional fire extinguishers at the second level warehouse office and lower level riser room, project related fire sprinkler and alarm permits need finaled, no other life safety items reviewed at this time, some phases of construction are still underway, permanent occupancy at the remodeled office area is not permitted at this time per discussion with the contractor.
FIR08-00348 INSP-Sprinkler Rough-in5/22/20085/22/20085/22/2008 2:32:25 PMPPART
Approved for ceiling cover as noted, existing system riser is current with an annual inspection.
FIR08-00163 INSP-Sprinkler Rough-in5/21/20085/22/20085/22/2008 12:35:19 PMPFAIL
Missing thrust blocks, ductile stub is not installed, point of connection to the first 90 is already covered by bedding material effectively concealing the work-pipe size and type, trace wire, depth of bury, etc. cannot be verified at this time due to cover.
BLD07-02934 FIRE-Final Inspection5/22/20085/22/20085/22/2008 12:05:00 PMPPASS
Items on correction notice verified for compliance, life safety passed. NOTE: no signature card available on site-has been misplaced per contractor.
BLD07-03070 FIRE-Final Inspection5/21/20085/22/20085/22/2008 11:53:36 AMAPART
Fire life safety final pending project related fire sprinkler work at the vault or compliance with IFC 2006 903.3.1.1.1 for exempt locations, also noted one EM light at the back exit hallway from the restrooms to be repaired and address number 510 posted on the correct doorway as discussed.
5/28/2008 - D. Hanneman denied a written request from the building owner to omit sprinkelrs from this vault. The Code does not exempt sprinklers in such spaces. (SLR)
FIR08-00160 INSP-Final Inspection5/21/20085/22/20085/22/2008 11:47:57 AMAFAIL
Missing coverage at the vault, remainder of tenant remodel work per the permit scope is acceptable.
FIR07-00606 INSP-Sprinkler Rough-in5/21/20085/22/20085/22/2008 11:02:32 AMAFAIL
Re-inspection completed for overhead rough-in at the second floor area I, noted several items still not corrected including seismic clearance at mains and block walls, missing or overspaced hangers, poorly attatched retaining straps, stairways are not finished, pendent heads at two locations in the corridor are overspaced off adjacent classroom entry vestibules. NOTE: Agreed to allow ceiling cover at the classrooms only due to contractor repairing missing hangers and ret. straps during the field inspection. See stamped plan set for annotated defficiencies.