ESC05-01560
| Aging Inspection | 5/22/2008 | 5/22/2008 | 5/23/2008 3:13:48 PM | | PASS |
|
|
Work has been completed. CAS #460
|
ESC05-01719
| Aging Inspection | 5/22/2008 | 5/22/2008 | 5/23/2008 1:53:52 PM | | CANC |
|
|
moved to a site final CAS #460
|
ESC05-01506
| Aging Inspection | 5/22/2008 | 5/22/2008 | 5/23/2008 1:52:33 PM | | DEFR |
|
|
moved to a site final CAS #460
|
ESC05-01499
| Aging Inspection | 5/22/2008 | 5/22/2008 | 5/22/2008 3:51:59 PM | | DONE |
|
|
Could not find address. CAS #460
|
ESC05-01486
| Site Final | 5/22/2008 | 5/22/2008 | 5/22/2008 3:29:16 PM | P | PASS |
|
|
Work complete. Site is stabilized. CAS #460
|
ESC05-01489
| Site Final | 5/22/2008 | 5/22/2008 | 5/22/2008 3:28:50 PM | P | PASS |
|
|
Work complete. Site is stabilized. CAS #460
|
ESC05-01485
| Site Final | 5/22/2008 | 5/22/2008 | 5/22/2008 3:28:28 PM | P | PASS |
|
|
Work complete. Site is stabilized. CAS #460
|
ESC05-01484
| Site Final | 5/22/2008 | 5/22/2008 | 5/22/2008 3:28:00 PM | P | PASS |
|
|
Work complete. Site is stabilized. CAS #460
|
ESC05-01487
| Site Final | 5/22/2008 | 5/22/2008 | 5/22/2008 3:27:23 PM | P | PASS |
|
|
Work complete. Site is stabilized. CAS #460
|
ESC05-01633
| Aging Inspection | 5/22/2008 | 5/22/2008 | 5/22/2008 2:48:08 PM | | DEFR |
|
|
Site final. CAS #460
|
ESC05-01633
| Site Preparation | 5/22/2008 | 5/22/2008 | 5/22/2008 2:48:03 PM | P | PASS |
|
|
Work complete. Site is stabilized. CAS #460
|
ESC05-01610
| Aging Inspection | 5/22/2008 | 5/22/2008 | 5/22/2008 2:40:12 PM | | DEFR |
|
|
to a site final. CAS #460
|
ESC05-01610
| Site Final | 5/22/2008 | 5/22/2008 | 5/22/2008 2:40:02 PM | P | PASS |
|
|
Work complete. Site is stabilized. CAS #460
|
ESC07-01477
| BMP Violation | 5/20/2008 | 5/22/2008 | 5/22/2008 2:29:10 PM | A | FAIL |
|
|
No issues have been dealt with yet. Called RP and gave him till noon tomorrow or a Stop work Order will be issued. CAS #460
|
ESC08-00202
| BMP Violation | 5/21/2008 | 5/22/2008 | 5/22/2008 1:33:09 PM | A | CANC |
|
|
All issues dealt with. Site looks good. CAS #460
|
ESC07-01312
| Complaint Inspection | 5/22/2008 | 5/22/2008 | 5/22/2008 1:10:26 PM | P | FAIL |
|
|
Per complaint from ACHD. 1. Clean up tracking off of street. 2. pickup all trash off of lots. 3. Clean D.I. 4. protect irragation ditch at front of project. Met with the RP over issues and told him to correct imeadiately. Will re-inspect 5/23/08 CAS #460
|
ESC07-01313
| Complaint Inspection | 5/22/2008 | 5/22/2008 | 5/22/2008 1:09:53 PM | P | FAIL |
|
|
Per complaint from ACHD. 1. Clean up tracking off of street. 2. pickup all trash off of lots. 3. Clean D.I. 4. protect irragation ditch at front of project. Met with the RP over issues and told him to correct imeadiately. Will re-inspect 5/23/08 CAS #460
|
ESC07-01314
| Complaint Inspection | 5/22/2008 | 5/22/2008 | 5/22/2008 1:09:36 PM | P | FAIL |
|
|
Per complaint from ACHD. 1. Clean up tracking off of street. 2. pickup all trash off of lots. 3. Clean D.I. 4. protect irragation ditch at front of project. Met with the RP over issues and told him to correct imeadiately. Will re-inspect 5/23/08 CAS #460
|
ESC07-01315
| Complaint Inspection | 5/22/2008 | 5/22/2008 | 5/22/2008 1:09:19 PM | P | FAIL |
|
|
Per complaint from ACHD. 1. Clean up tracking off of street. 2. pickup all trash off of lots. 3. Clean D.I. 4. protect irragation ditch at front of project. Met with the RP over issues and told him to correct imeadiately. Will re-inspect 5/23/08 CAS #460
|
ESC08-00160
| BMP Violation | 5/22/2008 | 5/22/2008 | 5/22/2008 10:12:07 AM | P | PASS |
|
|
(Duplicate. Prior inspection has the wrong Disposition) Due to the construction activities th entance and access control will dealt with once utilities are finished in those areas. ESC sign has been re-posted. CAS #460
|
ESC08-00160
| BMP Violation | 5/20/2008 | 5/22/2008 | 5/22/2008 10:02:08 AM | P | CANC |
|
|
Due to the construction activities th entance and access control will dealt with once utilities are finished in those areas. ESC sign has been re-posted. CAS #460
|
ESC07-01121
| BMP Violation | 5/22/2008 | 5/22/2008 | 5/22/2008 10:00:25 AM | A | FAIL |
|
|
Verbal Correction Notice 1. Need to protect all D.I. on project perimeter and in the parking lot. 2. Clean up all residual concrtete wash off of parking lot. 3. Clean up all trash on site. Spoke with RP over issues and will re-inspect on 5/23/08 CAS #460
|
ESC06-01078
| BMP Violation | 5/1/2008 | 5/22/2008 | 5/22/2008 9:55:41 AM | A | CANC |
|
|
met with RP and he gave me the schedule for all work on stabilizing the project and clean up of the project. It will work. CAS #460
|